Airports (Building Control) Amendment Regulations 2011 (No. 1)1

Select Legislative Instrument 2011 No. 75

I, PROFESSOR MARIE BASHIR, AC, CVO, Administrator of the Government of the Commonwealth of Australia, acting with the advice of the Federal Executive Council, make the following Regulations under the Airports Act 1996.

Dated 2 June 2011

MARIE BASHIR

Administrator

By Her Excellency’s Command

ANTHONY ALBANESE

Minister for Infrastructure and Transport

1 Name of Regulations

  These Regulations are the Airports (Building Control) Amendment Regulations 2011 (No. 1).

2 Commencement

  These Regulations commence on 1 July 2011.

3 Amendment of Airports (Building Control) Regulations 1996

  Schedule 1 amends the Airports (Building Control) Regulations 1996.

Schedule 1 Amendment

(regulation 3)

 

[1] Schedule 1

substitute

Schedule 1 Fees payable for building applications

(regulation 2.02)

Part 1 Adelaide and Parafield Airports

Item

Total estimated cost of proposed building or works ($)

Application fee ($)

1

Up to 25 000

750

2

25 001 to 50 000

750

3

50 001 to 100 000

750

4

100 001 to 200 000

1 200

5

200 001 to 300 000

1 800

6

300 001 to 400 000

2 400

7

400 001 to 500 000

3 000

8

500 001 to 1 000 000

6 000

9

1 000 001 to 2 000 000

12 000

10

2 000 001 to 3 000 000

18 000

11

3 000 001 to 4 000 000

24 000

12

4 000 001 to 5 000 000

30 000

13

5 000 001 to 10 000 000

60 000

14

10 000 001 to 20 000 000

120 000

15

20 000 001 to 30 000 000

180 000

16

30 000 001 to 40 000 000

210 000

17

40 000 001 to 50 000 000

210 000

18

50 000 001 or more

210 000

Part 2 Alice Springs Airport

Item

Total estimated cost of proposed building or works ($)

Application fee ($)

1

Up to 25 000

750

2

25 001 to 50 000

1 200

3

50 001 to 100 000

1 800

4

100 001 to 200 000

2 700

5

200 001 to 300 000

3 600

6

300 001 to 400 000

4 500

7

400 001 to 500 000

5 400

8

500 001 to 1 000 000

8 400

9

1 000 001 to 2 000 000

12 000

10

2 000 001 to 3 000 000

15 000

11

3 000 001 to 4 000 000

18 000

12

4 000 001 to 5 000 000

21 000

13

5 000 001 to 10 000 000

30 000

14

10 000 001 to 20 000 000

60 000

15

20 000 001 to 30 000 000

90 000

16

30 000 001 to 40 000 000

120 000

17

40 000 001 to 50 000 000

150 000

18

50 000 001 or more

210 000

Part 3 Brisbane, Archerfield and Gold Coast Airports

Item

Total estimated cost of proposed building or works ($)

Application fee ($)

1

Up to 25 000

1 200

2

25 001 to 50 000

1 800

3

50 001 to 100 000

2 400

4

100 001 to 200 000

3 600

5

200 001 to 300 000

4 500

6

300 001 to 400 000

5 400

7

400 001 to 500 000

6 300

8

500 001 to 1 000 000

8 400

9

1 000 001 to 2 000 000

12 000

10

2 000 001 to 3 000 000

15 000

11

3 000 001 to 4 000 000

18 000

12

4 000 001 to 5 000 000

21 000

13

5 000 001 to 10 000 000

30 000

14

10 000 001 to 20 000 000

60 000

15

20 000 001 to 30 000 000

90 000

16

30 000 001 to 40 000 000

120 000

17

40 000 001 to 50 000 000

150 000

18

50 000 001 or more

210 000

Part 4 Canberra Airport

Item

Total estimated cost of proposed building or works ($)

Application fee ($)

1

Up to 25 000

450

2

25 001 to 50 000

600

3

50 001 to 100 000

900

4

100 001 to 200 000

1 275

5

200 001 to 300 000

1 650

6

300 001 to 400 000

2 025

7

400 001 to 500 000

2 400

8

500 001 to 1 000 000

3 900

9

1 000 001 to 2 000 000

6 150

10

2 000 001 to 3 000 000

8 400

11

3 000 001 to 4 000 000

10 650

12

4 000 001 to 5 000 000

12 900

13

5 000 001 to 10 000 000

24 150

14

10 000 001 to 20 000 000

39 300

15

20 000 001 to 30 000 000

54 300

16

30 000 001 to 40 000 000

69 300

17

40 000 001 to 50 000 000

84 300

18

50 000 001 or more

99 300

Part 5 Darwin International Airport

Item

Total estimated cost of proposed building or works ($)

Application fee ($)

1

Up to 25 000

750

2

25 001 to 50 000

1 200

3

50 001 to 100 000

1 800

4

100 001 to 200 000

2 700

5

200 001 to 300 000

3 600

6

300 001 to 400 000

4 500

7

400 001 to 500 000

5 400

8

500 001 to 1 000 000

8 400

9

1 000 001 to 2 000 000

12 000

10

2 000 001 to 3 000 000

15 000

11

3 000 001 to 4 000 000

18 000

12

4 000 001 to 5 000 000

21 000

13

5 000 001 to 10 000 000

30 000

14

10 000 001 to 20 000 000

60 000

15

20 000 001 to 30 000 000

90 000

16

30 000 001 to 40 000 000

120 000

17

40 000 001 to 50 000 000

150 000

18

50 000 001 or more

210 000

Part 6 Hobart International Airport

Item

Total estimated cost of proposed building or works ($)

Application fee ($)

1

Up to 25 000

1 680

2

25 001 to 50 000

1 875

3

50 001 to 100 000

2 250

4

100 001 to 200 000

3 900

5

200 001 to 300 000

4 800

6

300 001 to 400 000

5 700

7

400 001 to 500 000

6 600

8

500 001 to 1 000 000

12 000

9

1 000 001 to 2 000 000

18 000

10

2 000 001 to 3 000 000

24 000

11

3 000 001 to 4 000 000

30 000

12

4 000 001 to 5 000 000

36 000

13

5 000 001 to 10 000 000

66 000

14

10 000 001 to 20 000 000

126 000

15

20 000 001 to 30 000 000

186 000

16

30 000 001 to 40 000 000

246 000

17

40 000 001 to 50 000 000

306 000

18

50 000 001 or more

429 000

Part 7 Launceston Airport

Item

Total estimated cost of proposed building or works ($)

Application fee ($)

1

Up to 25 000

1 680

2

25 001 to 50 000

1 875

3

50 001 to 100 000

2 250

4

100 001 to 200 000

3 000

5

200 001 to 300 000

4 125

6

300 001 to 400 000

4 875

7

400 001 to 500 000

5 625

8

500 001 to 1 000 000

9 375

9

1 000 001 to 2 000 000

19 575

10

2 000 001 to 3 000 000

24 375

11

3 000 001 to 4 000 000

31 875

12

4 000 001 to 5 000 000

39 375

13

5 000 001 to 10 000 000

76 875

14

10 000 001 to 20 000 000

151 875

15

20 000 001 to 30 000 000

226 875

16

30 000 001 to 40 000 000

301 875

17

40 000 001 to 50 000 000

376 875

18

50 000 001 or more

528 000

Part 8 Melbourne (Tullamarine), Essendon and Moorabbin Airports

Item

Total estimated cost of proposed building or works ($)

Application fee ($)

1

Up to 25 000

1 200

2

25 001 to 50 000

1 800

3

50 001 to 100 000

2 400

4

100 001 to 200 000

3 600

5

200 001 to 300 000

4 500

6

300 001 to 400 000

5 400

7

400 001 to 500 000

6 300

8

500 001 to 1 000 000

8 400

9

1 000 001 to 2 000 000

12 000

10

2 000 001 to 3 000 000

15 000

11

3 000 001 to 4 000 000

18 000

12

4 000 001 to 5 000 000

21 000

13

5 000 001 to 10 000 000

30 000

14

10 000 001 to 20 000 000

60 000

15

20 000 001 to 30 000 000

90 000

16

30 000 001 to 40 000 000

120 000

17

40 000 001 to 50 000 000

150 000

18

50 000 001 or more

210 000

Part 9 Perth and Jandakot Airports

Item

Total estimated cost of proposed building or works ($)

Application fee ($)

1

Up to 25 000

750

2

25 001 to 50 000

1 200

3

50 001 to 100 000

1 800

4

100 001 to 200 000

2 700

5

200 001 to 300 000

3 600

6

300 001 to 400 000

4 500

7

400 001 to 500 000

5 400

8

500 001 to 1 000 000

8 400

9

1 000 001 to 2 000 000

12 000

10

2 000 001 to 3 000 000

15 000

11

3 000 001 to 4 000 000

18 000

12

4 000 001 to 5 000 000

21 000

13

5 000 001 to 10 000 000

30 000

14

10 000 001 to 20 000 000

60 000

15

20 000 001 to 30 000 000

90 000

16

30 000 001 to 40 000 000

120 000

17

40 000 001 to 50 000 000

150 000

18

50 000 001 or more

210 000

Part 10 Sydney (Kingsford Smith), Camden and Bankstown Airports

Item

Total estimated cost of proposed building or works ($)

Application fee ($)

1

Up to 25 000

1 200

2

25 001 to 50 000

1 800

3

50 001 to 100 000

2 400

4

100 001 to 200 000

3 600

5

200 001 to 300 000

4 500

6

300 001 to 400 000

5 400

7

400 001 to 500 000

6 300

8

500 001 to 1 000 000

8 400

9

1 000 001 to 2 000 000

12 000

10

2 000 001 to 3 000 000

15 000

11

3 000 001 to 4 000 000

18 000

12

4 000 001 to 5 000 000

21 000

13

5 000 001 to 10 000 000

30 000

14

10 000 001 to 20 000 000

60 000

15

20 000 001 to 30 000 000

90 000

16

30 000 001 to 40 000 000

120 000

17

40 000 001 to 50 000 000

150 000

18

50 000 001 or more

210 000

Part 11 Townsville Airport

Item

Total estimated cost of proposed building or works ($)

Application fee ($)

1

Up to 25 000

1 200

2

25 001 to 50 000

1 800

3

50 001 to 100 000

2 400

4

100 001 to 200 000

3 600

5

200 001 to 300 000

4 500

6

300 001 to 400 000

5 400

7

400 001 to 500 000

6 300

8

500 001 to 1 000 000

8 400

9

1 000 001 to 2 000 000

12 000

10

2 000 001 to 3 000 000

15 000

11

3 000 001 to 4 000 000

18 000

12

4 000 001 to 5 000 000

21 000

13

5 000 001 to 10 000 000

30 000

14

10 000 001 to 20 000 000

60 000

15

20 000 001 to 30 000 000

90 000

16

30 000 001 to 40 000 000

120 000

17

40 000 001 to 50 000 000

150 000

18

50 000 001 or more

210 000

Note