TABLE OF CONTENTS

 

FOREWORD

 

SCOPE AND APPLICATION

1.

INTRODUCTION

1.1 

What are the prohibitions on asbestos in the workplace?

1.2 

Who has duties to manage and control asbestos or ACM?

1.3

The meaning of key terms

2.

MANAGING RISKS ASSOCIATED WITH ASBESTOS AND ACM

2.1 

What is involved in managing risks?

2.2

Identifying if asbestos or ACM is at the workplace

2.3

Assuming asbestos or ACM is present

2.4

Arranging a sample to identify asbestos

2.5

Indicating the presence of asbestos in the workplace

2.6

Assessing the risk of exposure

3.

ASBESTOS REGISTER

3.1

What is an asbestos register?

3.2

Reviewing and revising an asbestos register

3.3

Accessing an asbestos register

3.4

Transferring an asbestos register

4.

ASBESTOS MANAGEMENT PLAN

4.1

What is an asbestos management plan?

4.2

Reviewing an asbestos management plan

4.3

Accessing an asbestos management plan

5.

MANAGING OTHER ASBESTOS-RELATED RISKS

5.1

Naturally occurring asbestos

5.2

Contaminated sits

5.3

Demolition and refurbishment work

5.4

Asbestos-related work

5.5

Disposing of asbestos or ACM

3.9

Agricultural or veterinary chemical products

3.10

Products containing nanomaterials

6.

MANAGING EXPOSURE TO ASBESTOS OR ACM

6.1

Measuring the exposure standard

6.2

Health monitoring

6.3

Training workers about asbestos or ACM

6.4

Limited use of equipment

7.

CONTROLLING THE RISKS

7.1

Removing asbestos

7.2

Enclosing asbestos

7.3

Encapsulation and sealing asbestos

7.4

Tools and equipment

7.5

Safe work practices

7.6

Personal protective equipment

7.7

Laundering clothing

7.8

Cleaning up

 

APPENDIX A – SAMPLING PROCESS

 

APPENDIX B – EXAMPLES OF WARNING SIGNS AND LABELS

 

APPENDIX C – TEMPLATE OF AN ASBESTOS REGISTER

 

APPENDIX D – EXAMPLE OF AN ASBESTOS REGISTER

 

APPENDIX E – EXAMPLE OF ASBESTOS-RELATED WORK

 

APPENDIX F – RECOMMENDED SAFE WORKING PRACTICES


FOREWORD

This Code of Practice on how to manage and control asbestos in the workplace is an approved code of practice under section 274 of the Work Health and Safety Act 2011 (the WHS Act).

An approved code of practice is a practical guide to achieving the standards of health, safety and welfare required under the WHS Act and the Work Health and Safety Regulations 2011 (the WHS Regulations).

A code of practice applies to anyone who has a duty of care in the circumstances described in the code. In most cases, following an approved code of practice would achieve compliance with the health and safety duties in the WHS Act, in relation to the subject matter of the code. Like regulations, codes of practice deal with particular issues and do not cover all hazards or risks that may arise. The health and safety duties require duty holders to consider all risks associated with work, not only those for which regulations and codes of practice exist.

Codes of practice are admissible in court proceedings under the WHS Act and Regulations. Courts may regard a code of practice as evidence of what is known about a hazard, risk or control and may rely on the code in determining what is reasonably practicable in the circumstances to which the code relates.

The WHS Act and Regulations may be complied with by following another method, such as a technical or an industry standard, if it provides an equivalent or higher standard of work health and safety than the code.

An inspector may refer to an approved code of practice when issuing an improvement or prohibition notice. 

This Code of Practice is based on the draft code of practice developed by Safe Work Australia as a model code of practice under the Council of Australian Governments’ Inter-Governmental Agreement for Regulatory and Operational Reform in Occupational Health and Safety for adoption by the Commonwealth, state and territory governments.

A draft of that model code of Practice was released for public consultation on 7 December 2010 and was endorsed by the Workplace Relations Ministers’ Council on 10 August 2011.


SCOPE AND APPLICATION

This Code of Practice provides practical guidance for persons conducting a business or undertaking on how to manage risks associated with asbestos and asbestos containing material (ACM) at the workplace and thereby minimise the incidence of asbestos-related diseases such as mesothelioma, asbestosis and lung cancer.  

This Code of Practice  provides information on how to identify the presence of asbestos at the workplace and how to implement measures to eliminate or minimise the risk of exposure to airborne asbestos fibres.

In some cases, the most appropriate control measure determined may be to remove the asbestos. The Code of Practice: How to Safely Remove Asbestos provides further guidance for asbestos removalists so asbestos can be removed whilst eliminating, or where this is not possible, minimising the exposure of workers and other persons to airborne asbestos.

Other laws relating to matters such as environmental protection, public health, building and construction and local government regulation may apply in addition to the WHS Act and WHS Regulations.

Some chapters of this Code of Practice will apply to asbestos that is present in domestic premises when the premises become a workplace.

In providing guidance, the word ‘should’ is used in this Code of Practice to indicate a recommended course of action, while ‘may’ is used to indicate an optional course of action.

This Code of Practice also includes various references to sections of the WHS Act and Regulations to provide context with legal requirements. These references are not exhaustive. The words ‘must’, ‘requires’ or ‘mandatory’ indicate that these legal requirements exist and must be complied with.


1.  INTRODUCTION

Regulation 419 A person conducting a business or undertaking must not carry out or direct or allow a worker to carry out work involving asbestos if that work involves manufacturing, supplying, transporting, storing, removing, using, installing, handling, treating, disposing of or disturbing asbestos or asbestos contaminated material (ACM), except in prescribed circumstances.

NOTE:  The prohibition on the supply of asbestos also prohibits the sale of asbestos or ACM.

The final prohibition for asbestos in the workplace came into effect on 31 December 2003. These prohibitions do not apply if the work involving asbestos is any of the following:

Work involving asbestos-contaminated soil is not prohibited as long as a competent person has determined the soil does not contain any visible ACM or friable asbestos. If friable asbestos is visible, it should not contain more than trace levels of asbestos determined in accordance with AS4964:2004 Method for the qualitative identification of asbestos in bulk samples.

The management of naturally occurring asbestos (NOA) that stays in its natural state is not prohibited if managed in accordance with an asbestos management plan.

Although the ultimate goal of this prohibition is for all workplaces to be free of asbestos, it is only when these materials are being replaced or where they present a health risk that non-asbestos alternatives must be used. Caution needs to be taken when working with buildings constructed prior to 1990 or newer buildings that may have used recycled materials and may have reinstated old plant containing ACM gaskets and/or linings.

If asbestos or ACM is identified in a workplace and demolition or refurbishment work is going to be carried out, the asbestos or ACM must be removed if it is likely to be disturbed before the work starts. If other maintenance or service work is to be carried out at the workplace, removal of asbestos should be considered as a control measure.

Where removal is not reasonably practicable, other control measures must be implemented to minimise exposure, including encapsulation or sealing. 

In addition to the prohibition, there is also a restriction on who can remove asbestos. Asbestos removalists and their workers must be competent to carry out asbestos removal work and, except in limited circumstances, must be licensed. Further details on who can remove asbestos can be found in the WHS Regulations and the Code of Practice: How to Safely Remove Asbestos.

The importation of asbestos or materials containing asbestos into Australia is generally prohibited under the Customs (Prohibited Imports) Regulations 1956 (Customs PI Regulations).

To complement the ban on the importation, manufacture and use of all forms of asbestos and asbestos-containing products from 31 December 2003, the import prohibition on asbestos under the Customs PI Regulations was also introduced.

If plant or other materials are imported from countries where asbestos is not yet prohibited, a quality assurance system should be put in place to ensure they do not contain asbestos prior to supplying or using them in the workplace.

Further information on importing asbestos or any other customs matter is available on the Customs website http://www.customs.gov.au.

The WHS Act requires all persons who conduct a business or undertaking to ensure, so far as is reasonably practicable, that workers and other persons are not put at risk from work carried out as part of the business or undertaking. The WHS Regulations include specific obligations to manage and control asbestos and ACM at the workplace. These are summarised in the table below.

 

Duty holder

Responsibilities

Person conducting a business or undertaking (PCBU)

Control risk of exposure

  • must ensure, so far as is reasonably practicable, that exposure of a person at the workplace to airborne asbestos is eliminated, except in an area that is enclosed to prevent the release of respirable asbestos fibres and negative pressure is used. If this is not reasonably practicable, the exposure must be minimised so far as is reasonably practicable
  • must ensure the exposure standard for asbestos is not exceeded at the workplace.

Health monitoring

  • must ensure health monitoring is provided to a worker who is carrying out licensed removal work, other ongoing asbestos removal work or asbestos-related work and there is risk of exposure when carrying out that work
  • must ensure the health monitoring is carried out under the supervision of a registered medical practitioner and information as specified in the WHS Regulations is provided to that medical practitioner
  • must pay all expenses for health monitoring, obtain report and keep records of all health monitoring.

Training and use of equipment

  • must ensure that information, training and instruction provided to a worker is suitable and adequate and that it is provided in a way that is readily understandable by any person to whom it is provided
  • must ensure that, if a worker is either carrying out asbestos-related work or may be involved in asbestos removal work, they are trained in the identification and safe handling of asbestos and ACM and the suitable control measures
  • for workers who carry out work where NOA is likely to be found, training must be provided on hazards and risks associated with NOA.

Controlling the use of equipment

  • must not use, or direct or allow a worker to use, certain equipment on asbestos and ACM.

Asbestos-related work

  • must, if there is uncertainty as to whether work is asbestos-related work, assume asbestos is present or arrange for an analysis of a sample to be undertaken to determine if asbestos or ACM is present
  • must give information as specified in regulation 480 of the WHS Regulations to a person who is likely to be engaged to carry out asbestos-related work
  • must ensure the asbestos-related work area is separated from other work areas at the workplace, signs are used to indicate where the asbestos-related work is being carried out and barricades are used to delineate the asbestos-related work area
  • must ensure a competent person carries out air monitoring of the work area if there is uncertainty as to whether the exposure standard is likely to be exceeded
  • must ensure that decontamination facilities (including containers and labels labelled in accordance with the GHS) are available when asbestos-related work is being carried out
  • must ensure that asbestos waste is contained and labelled in accordance with the GHS before it is removed, and is disposed of as soon as practicable
  • must ensure, where personal protective equipment (PPE) is used and contaminated with asbestos, such PPE is sealed, decontaminated, labelled and disposed of in accordance with the WHS Regulations. If this is not reasonably practicable, the PPE must be laundered in accordance with the WHS Regulations. PPE that is not clothing and cannot be disposed of must be decontaminated and kept in a sealed container until it is reused for the purposes of asbestos-related work.


PCBU with management or control of a workplace

Identifying or assuming asbestos or ACM

  • must ensure, so far as is reasonably practicable, that all asbestos or ACM at the workplace is identified by a competent person or assume its presence
  • may identify asbestos or ACM by arranging a sample of the material to be analysed.

Indicating presence and location

  • must ensure the presence and location of asbestos or ACM identified (or assumed to be identified) at the workplace is clearly indicated (by a label if reasonably practicable).

Asbestos register

  • must ensure an asbestos register is prepared, maintained, reviewed and kept at the workplace. It must be readily available to workers, their health and safety representatives and other persons
  • must ensure, when management or control of the workplace is relinquished, a copy of the asbestos register is given to the person assuming management or control.

Asbestos management plan

  • must, where asbestos has been identified at the workplace, ensure an asbestos management plan is prepared, maintained and reviewed. It must be accessible to workers, their health and safety representatives and other persons.

Naturally Occurring Asbestos (NOA)

  • must manage the risks associated with NOA at the workplace and, where identified at the workplace or likely to be present, ensure that a written asbestos management plan is prepared, maintained and reviewed.

Demolition and Refurbishment Work

  • prior to demolition or refurbishment work starting, must review the asbestos register and ensure all asbestos that is likely to be disturbed is identified and removed so far as is reasonably practicable
  • must provide a copy of the asbestos register to the person carrying out the demolition or refurbishment work before the work commences
  • must, if an emergency occurs and a structure or plant is to be demolished, ensure that before the demolition occurs there is a procedure to reduce the risk of exposure to asbestos to below the exposure standard and notify Comcare about the emergency.

PCBU carrying out demolition or refurbishment work

Demolition and Refurbishment Work

  • must, prior to the demolition or refurbishment work being carried out:
  • obtain a copy of the asbestos register for the workplace from the person with management or control before the work commences
  • if an asbestos register is not available, ensure the structure or plant to be demolished or refurbished has been inspected by a competent person to determine if any asbestos or ACM is fixed to or installed (or assume its presence)
  • where asbestos is determined to be fixed to or installed, tell the occupier, owner (if at a domestic premises) or the person with management or control in any other case
  • ensure asbestos at domestic premises that is likely to be disturbed by the demolition or refurbishment is identified and, if reasonably practicable, removed before the work starts
  • if an emergency occurs at domestic premises where asbestos is identified (or assumed) and it must be demolished, ensure there is a procedure to reduce the risk of the exposure to asbestos to below the exposure standard and notify Comcare about the emergency.

In some cases, there may be more than one person with management or control of a workplace. For example:

Airborne asbestos means any fibres of asbestos small enough to be made airborne. For the purposes of monitoring airborne asbestos fibres, only respirable fibres are counted.

Asbestos means the asbestiform varieties of mineral silicates belonging to the serpentine or amphibole groups of rock-forming minerals, including actinolite asbestos, grunerite (or amosite) asbestos (brown), anthophyllite asbestos, chrysotile asbestos (white), crocidolite asbestos (blue) and tremolite asbestos.

Asbestos containing material (ACM) means any material or thing that, as part of its design, contains asbestos.

Asbestos-contaminated dust or debris (ACD) means dust or debris that has settled within a workplace and is (or assumed to be) contaminated with asbestos.

Asbestos-related work means work involving asbestos (other than asbestos removal work to which Part 8.7 of the WHS Regulations applies) that is permitted under the exceptions set out in regulation 419(3), (4) and (5).

Asbestos removalist means a person conducting a business or undertaking who carries out asbestos removal work.

Asbestos removal work means:

Competent person means a person who has acquired, through training, qualification or experience, the knowledge and skills to carry out the task.

Exposure standard for asbestos is a respirable fibre level of 0.1 fibres/ml of air measured in a person’s breathing zone and expressed as a time weighted average fibre concentration calculated over an eight-hour working day and measured over a minimum period of four hours in accordance with:

Friable asbestos means material that is in a powder form or that can be crumbled, pulverised or reduced to a powder by hand pressure when dry, and contains asbestos.

GHS means Globally Harmonised System of Classification and Labelling of Chemicals, Third revised edition, published by the United Nationals as modified under Schedule 6.

In-situ asbestos means asbestos or ACM fixed or installed in a structure, equipment or plant but does not include naturally occurring asbestos.

NATA-accredited laboratory means a testing laboratory accredited by the National Association of Testing Authorities (NATA), Australia, or recognised by NATA either solely or with someone else.

Naturally occurring asbestos (NOA) means the natural geological occurrence of asbestos minerals found in association with geological deposits including rock, sediment or soil.

Non-friable asbestos means material containing asbestos that is not friable asbestos, including material containing asbestos fibres reinforced with a bonding compound.

Respirable asbestos means an asbestos fibre that:


2. MANAGING RISKS ASSOCIATED WITH ASBESTOS AND ACM

Regulation 420:   A person conducting a business or undertaking must ensure, so far as is reasonably practicable, exposure of a person at the workplace to airborne asbestos is eliminated. If this is not reasonably practicable, the exposure must be minimised so far as is reasonably practicable.

The exposure standard for asbestos must not be exceeded at the workplace.

Managing the risks associated with asbestos involves:

When choosing the most appropriate control measure, the following hierarchy of controls must be considered:

A combination of these controls may be required in order to adequately manage and control asbestos or ACM. Chapter 7 of this Code provides more information on the different control measures that can be used.

General guidance on the risk management process is available in the Code of Practice: How to Manage Work Health and Safety Risks.

Section 47: The WHS Act requires the person conducting a business or undertaking to consult, so far as is reasonably practicable, with workers who carry out work who are (or are likely to be) directly affected by a work health and safety matter.

Section 48:  If the workers are represented by a health and safety representative, the consultation must involve that representative.

Consultation with workers and their health and safety representatives is a critical part of managing work health and safety risks.

Consulting with and involving workers in the identification and safe handling of asbestos can assist in ensuring that safety instructions and safe work practices are complied with.

Health and safety representatives must have access to relevant information on matters that can affect the health and safety of workers, for example asbestos exposure data and the asbestos register.

Section 46: The WHS Act requires that persons conducting a business or undertaking consult, cooperate and coordinate activities with all other persons who have a work health or safety duty in relation to the same matter, so far as is reasonably practicable.

Sometimes there may be other businesses that are involved in the same activities or share the same workplace. For example:

The owner of an arcade is renovating one of the shops for a new tenant to move into. The building owner has engaged a number of contractors to carry out the renovation work including demolishing a wall.

The building owner has management and control over the workplace and is responsible for ensuring the current asbestos register is updated due to the work that is being carried out. The building owner consults other tenants that may be affected by the renovation work on the identification of asbestos and what will need to be done if asbestos is disturbed.

As the work begins, the building owner, contractors and tenants all cooperate with each other and coordinate their activities to protect any persons from potential exposure to asbestos.

Further guidance on consultation is available in the Code of Practice: Work Health and Safety Consultation, Cooperation and Coordination.

This section does not apply to naturally occurring asbestos (NOA).

Regulation 422:  A person with management or control of a workplace must ensure asbestos or ACM at the workplace is identified by a competent person.

Identifying asbestos or ACM is the first step in managing the risk of exposure to asbestos in the workplace. As there may be more than one person in the workplace responsible for this duty, it is important that all duty holders consult, cooperate and coordinate with each other as well as consulting with workers and health and safety representatives, for example the person with control of the workplace may carry out the task of identifying asbestos with the person who has day-to-day management of the workplace to ensure it has been done accurately.

If the person with management or control of the workplace assumes that asbestos or ACM is present, or if they have reasonable grounds to believe that asbestos is not present, a competent person does not need to be engaged to make this decision.

The WHS Regulations define a competent person to be someone who has acquired knowledge and skills to carry out the task through training, a qualification or experience. This may mean that the competent person who can identify asbestos is:

There may be a person within the business who is competent to identify asbestos. If there is not, an external competent person should be engaged. Persons who may be considered to be competent in the identification of asbestos include:

The person who is carrying out the task of identifying asbestos should have all relevant information so they can correctly identify where asbestos is located in the workplace. For example, obtaining information on the products used in making the building, structure or plant, including building plans, design specifications, and correspondence with builders and plant manufacturers.  Workers in the workplace may also be able to assist the person with this task.

There are a number of factors that may be taken into account to identify or assume that asbestos is present in a workplace. These include:

When was the building constructed?

Asbestos was widely used as construction and insulation material in buildings until the late 1980s when bans on its manufacture and use were put in place. However, the use of asbestos was only completely prohibited on 31 December 2003. As the bans were not absolute prior to 2003 and building materials may have been stockpiled, stored, or recycled and used, it is possible that asbestos may be present in buildings that were constructed up to 31 December 2003 and possibly later.

Were there any refurbishments or additions to the building prior to 31 December 2003?

Any refurbishment or extensions to the original building prior to 1990 and potentially up to 31 December 2003 may have involved the use of asbestos. Even if the original parts of the building did not contain asbestos, it should not be assumed that subsequent additions have no asbestos.

What type of material was used to construct the building?

The main construction materials used are made from timber, brick, steel and cement sheet. If cement sheet is present and was installed up until 1990, it is likely to contain asbestos bonded to the cement particles. For example, a roof made from corrugated cement sheeting is likely to contain asbestos. Areas of buildings that are prone to wet conditions may contain asbestos in the walls and floors due to its hardiness and waterproofing qualities compared to other materials. For example, bathrooms, toilets and laundries may have asbestos sheeting or vinyl tiles. Likewise, pipes throughout the building that carry water and sewage may also contain asbestos.

Talk to designers, manufacturers or suppliers of plant, or refer to design plans

Asbestos may be present in specific parts of the plant in a workplace as it was used in gasket and friction brake products. Despite a large reduction in its use, chrysotile asbestos was still being used in some specific applications until recent years, including rotary vane vacuum pumps and in gaskets for certain types of equipment. If there is plant that was designed, built and installed prior to 1 January 2004, the supplier, manufacturer or designer of the plant should be consulted to find out if asbestos is present and, if possible, obtain this advice in writing. If this is not possible, review the design plans and seek advice from an experienced engineer or plant designer. Quality assurance systems or checks should be in place to confirm whether asbestos is present.

Talk to workers who have worked at the workplace for a long time

Speaking with experienced workers will assist in the identification process as they may be aware of the history of the building, including its age, construction, renovation or repairs, and may know where asbestos is located in the workplace.

Visually inspect the workplace to identify asbestos, ACM and inaccessible areas

 

A thorough inspection of all areas of the workplace must be conducted, including all buildings, structures, ceiling spaces, cellars, shafts, storage areas and wall cavities.

Material needs to be considered to contain asbestos unless proven otherwise if:

  • it cannot be identified
  • there is uncertainty as to whether it contains asbestos
  • it is inaccessible.

The design plans for a building, structure, ship or plant may assist in identifying inaccessible areas, as would discussion with builders, architects, manufacturers of plant and maintenance workers. Knowledge of materials used in the construction of the building or experience and findings from inspections of similar sections of the building (or similar buildings) may also assist.

Take notes and photographs

Taking notes and photographs while the inspection is being conducted can assist in producing the asbestos register.


This section does not apply to NOA.

Regulation 422:  A person with management or control of a workplace must:

It is not necessary to engage a competent person to identify asbestos if the person with management or control of the workplace assumes that asbestos is present or if that person has reasonable grounds to believe that asbestos is not present.

If there is uncertainty as to whether asbestos is present in any part of a structure or plant, the person with management or control of the workplace can either assume asbestos is present and treat it with appropriate caution based on the level of risk or have a sample analysed. If it is assumed to be asbestos, it is considered to be asbestos for legal purposes. There is no need to take a sample for analysis and identification in all circumstances.

This means the suspect material can remain undisturbed and the time and cost of sampling and analysis is avoided.

The person with management or control of a workplace can assume asbestos or ACM is not present as long as this assumption is based on reasonable grounds, which may include:

Once the presence and location of asbestos has been assumed:

If there are inaccessible areas in the workplace that a competent person has identified as likely to have asbestos or ACM, it must be assumed they contain asbestos until they are accessed and it is determined whether asbestos is present or not.

As a general rule, an inaccessible area is an area that cannot be accessed during normal daily activities or routine maintenance. The following areas are not regarded as ‘inaccessible areas’ and must be inspected or assumed to contain asbestos:

Accessing fire door and security safe cores to determine whether they contain asbestos may create a risk, for example drilling can result in the release of airborne asbestos. If this is the case, cores should not be accessed and must be assumed to contain asbestos until otherwise proven (for instance, during maintenance when access is obtained) or information is obtained from the supplier. Fire doors may have a compliance tag on the door jamb stating the fire rating and a compliance date. This can provide an indication of whether the door is likely to contain asbestos.

This section does not apply to NOA.

Regulation 423:  A person with management or control of a workplace may identify asbestos or ACM by arranging for a sample of material at the workplace to be analysed for the presence of asbestos or ACM.

A sample must only be analysed by:

It can be difficult to tell whether a material contains asbestos simply by looking at it, unless it is labelled. If a material has been imported from overseas, it may not be labelled as containing asbestos or it may only be labelled if the materials contain more than 10% asbestos. Therefore, a sample should be taken and analysed unless the decision was made to assume it is asbestos. 

Only a competent person may take the samples for analysis because of the increased health risk of fibres being released during the process. If the sampling process is conducted incorrectly, it can be more hazardous than leaving the material alone. All asbestos samples must be analysed by a NATA-accredited laboratory or one that is approved by Comcare. Any sample taken should be sealed within a container, or a 200 µm polythene bag, and appropriately labelled.

Once the results of the sampling are known, the person with management or control of the workplace must ensure the asbestos register is updated indicate that the material is asbestos or is assumed to be.

If asbestos is stable, non-friable and will not be disturbed, it should be left alone. Only material that is damaged or will be disturbed should be sampled. If the material may contain asbestos and it is decided not to take samples, an assumption must be made that the material contains asbestos.

Appendix A provides a procedure that a competent person can follow when undertaking sampling.

This section does not apply to NOA.

Regulation 424:  A person with management or control of a workplace must ensure the presence and location of asbestos or ACM identified at the workplace is clearly indicated. If reasonably practicable, the asbestos or ACM must be indicated by a label.

All identified or assumed asbestos, including where the asbestos is inaccessible, must be clearly indicated. If it is reasonably practicable, labels must be used to identify the material as containing asbestos. However, signs may be more appropriate to use.

Examples of labels or signs that can be used to indicate the location or presence of asbestos or ACM are shown at Appendix B. These examples provide an indication of the words that may be usedthese words are not mandatory.

If labels can be used, a competent person should determine the number and positions of the labels required. The location of labels should be consistent with the location listed in the asbestos register.

If a risk assessment suggests asbestos may be disturbed or people are likely to be exposed and it is not reasonably practicable to label asbestos directly, a prominent warning sign must be posted in its immediate vicinity. For example, if floor tiles have been identified as containing asbestos, an appropriate warning sign may be displayed on an adjacent wall.

All warning signs should comply with AS 1319 Safety Signs for the Occupational Environment.

Any areas of a workplace that contain asbestos, including plant, equipment and components, should be signposted with warning signs to ensure the asbestos is not unknowingly disturbed without the correct precautions being taken. These signs should be weatherproof, constructed of light-weight material and adequately secured. Signs should be placed at all the main entrances to the work areas where asbestos is present.

Where direct marking of asbestos is not possible, identifying the presence and location of asbestos to workers such as plumbers, electricians and carpenters before they commence work may be achieved by implementing a permit-to-work system. The presence and location of the asbestos should be entered on site plans and the asbestos register and be accessible to all workers to ensure they are aware of the presence of asbestos.

This section does not apply to NOA.

If asbestos or ACM is in good condition and left undisturbed, it is unlikely that airborne asbestos will be released into the air and the risk to health is extremely low. It is usually safer to leave it and review its condition over time. However, if the asbestos or ACM has deteriorated, has been disturbed, or if asbestos-contaminated dust is present, the likelihood that airborne asbestos will be released into the air is increased.

The type of material that binds asbestos fibres will influence the potential for airborne asbestos to be released into the air from different asbestos or ACM. For example, a loosely bound sprayed (or limpet) coating is more likely to release fibres when disturbed than asbestos cement in which fibres are firmly bound.

The following list ranks different types of asbestos according to the likelihood that airborne asbestos can be released into the air if it has deteriorated or been disturbed. The potential risk to health is greater for items higher up the list if people are exposed to airborne asbestos, but any of the materials listed can produce asbestos fibres if they are disturbed.

 

Higher likelihood of airborne fibres

Asbestos-contaminated dust (including dust left in place

after past asbestos removal)

Sprayed (limpet) coatings/loose fill

Lagging and packings (that are not enclosed)

Asbestos insulating board

Rope and gaskets

Millboard and paper

Asbestos cement

Floor tiles, mastic and roof felt

Decorative paints and plasters

 

Lower likelihood of airborne fibres

 

When deciding if there is a risk to health from asbestos, consider whether the asbestos or ACM is:

A visual inspection of the material, its location and an understanding of the work practices at the workplace will assist this decision.

Asbestos-related work activities (including maintenance) plus unusual and infrequent activities (such as emergency activities) need to be considered. Also take into account the proximity of the asbestos or ACM to where employees work, as this can affect the potential for exposure if asbestos fibres become airborne.

The following are examples of activities that could pose a risk to health:


3. ASBESTOS REGISTER

This chapter does not apply to domestic premises or NOA.

Regulation 425: A person with management or control of a workplace must ensure an asbestos register is prepared and kept at the workplace. The asbestos register must be maintained, to ensure the information in the register is up to date.

Note: An asbestos register is not required to be prepared when:

The asbestos register is a document that lists all identified (or assumed) asbestos in a workplace. The asbestos register must:

Appendix C provides a template of an asbestos register, while Appendix D provides an example of how it should be completed.

A comprehensive asbestos register may also include:

It may also be useful to attach photographs or drawings to visually show the location of the asbestos or ACM in the workplace.

 

If an asbestos register already exists at the workplace there is no need to create another one. The existing register can be reviewed and revised.

Persons conducting a business or undertaking who are carrying out or intend to carry out work at a workplace, should obtain the current asbestos register and identify any asbestos or ACM that they have management or control of (for example, asbestos in items of plant). The person with management or control of the workplace should be advised if any asbestos or ACM is identified and not included in the asbestos register for the workplace.

If workers consider that the work they are about to do will disturb asbestos, they should talk to the person with management and control of the workplace or their health and safety representative.

In some cases it may not be necessary to include asbestos or ACM that is only temporarily present in the workplace. For example, if plant that contains asbestos is being repaired at the workplace but it is only there for a short period while being repaired, it does not need to be recorded in the asbestos register. However, if plant is often at the workplace (for example, where the company specialises in repairing plant that typically contains asbestos), it would be important to include this in the asbestos register. Note that where work involving asbestos is carried out, there are requirements to ensure the safety of the worker.

An asbestos register is not required if a workplace has been constructed after 31 December 2003 or if no asbestos has been identified.

If there is no asbestos register at the workplace but asbestos is identified during the course of any work being carried out, the person with management or control of the workplace should be advised and must then identify it (or ensure a competent person identifies it) and prepare a register.

As there will be no asbestos register at a domestic premise, the homeowner or landlord must be advised if asbestos is identified and appropriate action taken. 


Regulation 426:  A person with management or control of a workplace must ensure an asbestos register is reviewed and where necessary revised by a competent person if:

The register should be reviewed at least once every five years to ensure it is kept up to date.

When reviewing the asbestos register, the person should carry out a visual inspection of the asbestos and ACM listed to determine its condition and revise the asbestos register as appropriate. Previous asbestos registers and records relating to asbestos removal jobs, for instance clearance certificates, can assist in identifying all asbestos and ACM in the workplace.

Regulation 427: The person with management or control of the workplace must ensure the asbestos register is readily accessible to:

Where work is being carried out or is about to be carried out at the workplace by a person conducting a business or undertaking and that work involves a risk of exposure to airborne asbestos, the person with management or control of the workplace must provide a copy of the asbestos register to that person.

A copy of the asbestos register should be kept at the workplace to ensure it is accessible.   


Regulation 428: If the person with management or control of a workplace plans to relinquish management or control (for instance, selling the workplace or the business or undertaking), they must ensure, so far as is reasonably practicable, that a copy of the asbestos register is given to the person who is assuming management or control of the workplace.


4. ASBESTOS MANAGEMENT PLAN

Regulation 429: A person with management or control of a workplace must ensure a written asbestos management plan is prepared for the workplace if asbestos or ACM has been identified or assumed present, or is likely to be present from time to time at the workplace.

The asbestos management plan must be maintained to ensure the information is up to date.

This requirement does not apply to domestic premises.

An asbestos management plan sets out how asbestos or ACM that is identified at the workplace will be managed, for example what, when and how it is going to be done.

An asbestos management plan must include:

Other information that may be included in the asbestos management plan is:

Regulation 430: The person with management or control of the workplace must ensure the asbestos management plan is reviewed and, if necessary, revised at least once every five years or when:

Regulation 429: The person with management or control of the workplace must ensure the asbestos management plan is readily accessible to:

The asbestos management plan should be kept at the workplace to ensure it is accessible. 


5. MANAGING OTHER ASBESTOs-related risks

Regulations 431-434: A person with management or control of a workplace must manage the risks associated with naturally occurring asbestos (NOA) at the workplace.

If NOA is identified at the workplace or is likely to be present from time to time, a written asbestos management plan must be prepared and maintained to ensure the information is up-to-date.

In the majority of workplaces, the asbestos that is encountered and poses a risk to health and safety will be found in manufactured products. However, some workplaces may have to deal with asbestos in its natural state. NOA may be encountered in road building, site and construction work, and other excavation activities. Asbestos may occur in veins within rock formations.

Due to the difficulties in fully describing the location and extent of a NOA deposit in an asbestos register, there is no requirement for NOA be listed in an asbestos register. However, any NOA identified or assumed at a workplace must be included on the asbestos management plan for the workplace or be the subject of a new asbestos management plan. This is to ensure steps are put in place, as with all other asbestos encountered in workplaces, to ensure that risks of exposure from NOA are assessed and managed.

When preparing an asbestos management plan, the following should be considered:

Information on the contents, review and accessibility of the asbestos management plan can be found in Chapter 4 of this Code.

Ongoing management of NOA may be determined with the aid of an air monitoring program to assess asbestos exposure levels and specific risk control measures.

The person with management or control of a workplace must ensure the release of airborne asbestos is minimised. This can be done by:

Training on the hazards and risks associated with NOA must be provided to workers who carry out work where NOA is found.

Section 6.3 of this Code provides further information on training workers about asbestos.

Sites contaminated with asbestos become a workplace when work is carried out there. The WHS Regulations require that, where asbestos is identified as contaminating a workplace, a register and asbestos management plan be created for the site.

The management and remediation of sites contaminated with asbestos from illegal dumping and demolition is a specialised task. In some instances, site remediation may entail removal of asbestos and ACM from the site; in other cases this may not be practicable, and other management strategies should be used. Engaging specialists who may include asbestos removalists is highly recommended for all but the most minor of non-friable contaminations.

The Assessment of Site Contamination National Environmental Protection Measure (NEPM) http://www.ephc.gov.au/contam sets out the general principles for assessment and remediation of sites contaminated with a number of hazardous materials including asbestos. It is recommended that a person conducting a business or undertaking who has a workplace that is, or is suspected of being, contaminated with asbestos should engage specialists in accordance with the competencies found in the NEPM.

This section applies to the demolition or refurbishment of a structure or plant constructed or installed before 31 December 2003.

Regulations 447-457:  Prior to any demolition or refurbishment work being carried out, a person with management and control of a workplace must:

The person conducting a business or undertaking who will carry out demolition or refurbishment at a workplace must obtain a copy of the asbestos register before they commence the work.

Examples of demolition may include:

Examples of refurbishment may include the partial dismantling of:

Demolition and refurbishment work does not include minor routine maintenance work, or other minor work.

When reviewing the asbestos register, the person with management or control of the workplace or plant should consider the following questions:

If the asbestos register identifies that asbestos or ACM is present, the person with management or control of the workplace must ensure all asbestos likely to be disturbed is identified and removed, so far as is reasonably practicable, before the demolition or refurbishment work starts.

The WHS Regulations allow for the demolition of part of a structure or plant in order to access insitu asbestos so it can be removed. For example, part of a wall may be demolished to access asbestos located in the wall cavity so it can be removed prior to further demolition.

For demolition work, if an emergency occurs, the person with management or control of the workplace must ensure a procedure is developed before the demolition work starts. The procedure must outline how to minimise the risk of exposure of workers and persons in the vicinity of the demolition site and ensure the exposure standard is not exceeded, so far as is reasonably practicable. The person must also provide Comcare with written notice of the emergency immediately after they become aware of the emergency and before the demolition starts.

 

NOTE:  An emergency can occur if a building, structure or plant is structurally unsound or a collapse of the building, structure or plant is imminent.

If there is no register for the workplace, the person who is carrying out the demolition or refurbishment work must not carry out the work until a competent person determines whether asbestos or ACM is fixed to or installed in the structure or plant.

If a competent person has reasonable grounds to be uncertain as to whether or not asbestos is present, before commencing demolition or refurbishment work the person carrying out the work must assume it is present. If it is determined or assumed to be present, the person carrying out the work must inform the occupier or owner (if it is domestic premises) or the person with management or control in any other case.

When a person has been engaged to conduct demolition or refurbishment at a domestic premise, it becomes the workplace of that person. Consequently, that person must identify and, if necessary, remove asbestos before work commences. The WHS Regulations place no duties on the homeowner.

If an emergency occurs, the person carrying out the demolition work at the domestic premise must ensure, so far as is reasonably practicable, that before the demolition work starts a procedure is developed that will explain how to minimise the risk of exposure of workers and persons in the vicinity of the demolition site and ensure the exposure standard is not exceeded, so far as is reasonably practicable. The person must also provide Comcare with written notice of the emergency immediately after they become aware of the emergency and before the demolition starts.


 

Regulations 478-484:  While work with asbestos is generally prohibited, the WHS Regulations allow work to occur on asbestos in certain circumstances: this is referred to as asbestos-related work.

Under the WHS Regulations, asbestos-related work includes:

When undertaking asbestos-related work activities, the WHS Regulations require that it only be performed in accordance with the following requirements:

Appendix E provides an example of asbestos-related work. 

If there is uncertainty as to whether asbestos is present or used in a certain activity at the workplace, the person with management or control of the workplace must assume asbestos is present and treat the activity as asbestos-related work or arrange for a sample to be analysed to determine if asbestos is present.

If asbestos is identified or assumed to be present, it is essential that the asbestos register be obtained and a decision made as to whether work can be done without disturbing the asbestos, for example:

It is also essential to ensure all people carrying out the work have the appropriate training (refer to Section 6.3 of this Code), correct tools (refer to Section 6.4 of this Code), PPE including clothing, decontamination materials, labels and signs ready at the workplace before any work commences that may disturb the asbestos and to minimise the number of people in the area. For example:

Before commencing any asbestos-related work, plastic sheeting may need to be placed on the floor and any other surfaces that may become contaminated with asbestos dust. At a minimum, heavy-duty 200 µm (micron) thick plastic sheeting should be used for this purpose.

Whatever the control method used, it should be effective in making all maintenance workers aware of the presence of asbestos and preventing any work activity that might expose them, or others nearby, to airborne asbestos. Particular attention should be paid to controlling work activities that affect inaccessible areas listed in the asbestos register, such as wall cavities and ceiling spaces.

Control measures include the following:

Administrative controls are systems of work or work procedures designed to eliminate or minimise risk. These controls are lower order controls that cannot be relied upon to be as effective as the higher order controls such as elimination, isolation and engineering. This is because administrative controls are systems or procedures that rely on human behaviour to be effective and can easily fail. Administrative control measures must be understood, implemented and maintained. This requires training, information and supervision for workers but the control measure can still fail if procedures are not followed or understood.

For some activities, administrative controls are the only practicable controls that can be implemented. An example of an administrative control for asbestos-related work is a procedure for collecting samples of ACM for the purpose of analysis. Collecting the samples may involve breaking or dislodging ACM, which can lead to the release of airborne asbestos fibres and consequently a risk to health.

A safe work procedure for this task would include actions such as:

For the administrative control measure to be effective and reduce risk, the person conducting the sampling must understand the risk and implement all of the procedure. If the procedure is not followed, the health of the person conducting the sampling and others in the workplace may be at risk.

Appendix F outlines examples of safe that are likely to disturb asbestos and control measures that eliminate or minimise exposure to airborne asbestos, when carrying out service and maintenance tasks.

Although PPE can be effective in controlling the risk from airborne asbestos fibres, the successful implementation and maintenance of this control measure requires further action and resources, including:

Disposable coveralls need to be of a suitable standard to prevent penetration of asbestos fibres, so far as is practicable. Disposable coveralls rated type 5, category 3 (prEN ISO 13982-1) or the equivalent would meet this standard. Any clothing worn under coveralls must be disposed of or suitably bagged for laundering as asbestos-contaminated clothing.

There are additional responsibilities related to the removal and disposal of asbestos, which are detailed in the Code of Practice: How to Safely Remove Asbestos, for example competency and licensing requirements.

Individual components and wiping rags must be placed in plastic bags, tying each bag separately prior to placing them in the container. Disposal bags need to be heavy duty (200 µm), made of clear plastic and marked with the label ‘Caution Asbestos – Do not open or damage bag. Do not inhale dust’. Asbestos waste awaiting disposal must be stored in closed containers (for example, 60 or 200 litre steel drums with removable lids or sealed skip).

Asbestos waste must be transported and disposed of in accordance with the relevant state or territory Environment Protection Authority (EPA) requirements. Asbestos waste can only be disposed of at a site licensed by the EPA and it must never be disposed of in the general waste system.


6. MANAGING EXPOSURE TO ASBESTOS OR ACM

Airborne respirable fibre concentrations can be estimated using available data (for example, monitoring reports, data from scientific literature) or past experience (for example, monitoring reports) of the process in question. In cases of doubt, it may be necessary to confirm the estimates by measurement using the Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Fibres [NOHSC: 3003 (2005)].

Exposure monitoring measures the levels of respirable fibres in the breathing zone of the worker while work is being undertaken. Exposure monitoring must be carried out by a competent person, who may include a licensed asbestos assessor or a person who has undertaken the endorsed unit of competency for licensed asbestos assessors. An occupational hygienist who has experience in asbestos exposure monitoring may also be used. 

Where exposure monitoring is carried out, it is good practice to stop work and investigate the cause if the level of airborne asbestos in the breathing zone reaches half the exposure standard.

Although the need for exposure air monitoring will depend on the particular circumstances, the results may assist in assessing risks associated with asbestos.

Other forms of air monitoring that are relevant to asbestos work are discussed in more detail in the Code of Practice: How to Safely Remove Asbestos. These include:


Regulations 435-444: A person conducting a business or undertaking must ensure health monitoring is provided to a worker if they are carrying out licensed asbestos removal work, other ongoing asbestos removal work or asbestos-related work and are at risk of exposure to asbestos when carrying out the work.

Health monitoring includes a medical examination to provide an initial baseline medical assessment. Health monitoring must include the following (unless another form of health monitoring is recommended by a registered medical practitioner):

Workers must be informed of any health monitoring requirements before the worker carries out work that may expose them to asbestos.

Where a worker is at risk of exposure to asbestos due to work other than licensed asbestos removal, health monitoring must also be undertaken. Examples of work where there is a risk of exposure include ongoing unlicensed removal work, undertaking maintenance work on ACM regularly as part of another job (for instance, electricians or building maintenance staff in older buildings) and carrying out asbestos-related work. The need for health monitoring for these workers should be determined on the basis of:

If a worker is carrying out licensed asbestos removal work, the health monitoring must be conducted prior to the worker commencing the work. Health monitoring should also be provided to the worker at regular intervals after commencing the asbestos-related work but at least once every two years.

Health monitoring must be carried out under the supervision of a registered medical practitioner with the relevant competencies. Prior to deciding who the registered medical practitioner will be, the person conducting a business or undertaking must consult the worker.

The person conducting a business or undertaking must pay all expenses relating to health monitoring.

Where there are two or more persons that have a duty to provide health monitoring to a worker, they may choose that one person organises health monitoring (known as the person who commissions the health monitoring), however the costs must be shared equally between each person unless they agree otherwise.

The person who commissions health monitoring must provide the following information to the registered medical practitioner:

A person who commissions health monitoring must take all reasonable steps to obtain a report from the registered medical practitioner as soon as practicable after the monitoring is carried out. 

The health monitoring report must include the following information:

That person must also give a copy of the report, as soon as reasonably practicable after obtaining it from the medical practitioner, to:

Reports must be kept as a confidential record for at least 40 years after the record is made and identified as a formal record for the particular worker. The report and results must not be disclosed to anyone unless the worker has provided their written consent. However, if the person was releasing the record under a duty of professional confidentiality, the worker’s written consent is not required.


Regulation 39:  A person conducting a business or undertaking must ensure that information, training and instruction provided to a worker is suitable and adequate, having regard to:

The person must, so far as is reasonably practicable, ensure the information, training and instruction is provided in a way that is readily understandable by any person to whom it is provided.

Regulation 445:  A person conducting a business or undertaking must ensure workers who they reasonably believe may be involved in asbestos removal work in the workplace or the carrying out of asbestos-related work are trained in the identification, safe handling and suitable control measures for asbestos and ACM.

This training may include the following topics:

 

This training is more general than the training that a worker undertaking asbestos removal work would receive. Workers who are undertaking licensed asbestos removal work are required to complete specific units of competency. Further information on these specific training requirements is available in the Code of Practice: How to Safely Remove Asbestos.

Records of all training must be kept while the worker is carrying out the work and for five years after the day the worker stops carrying out the work. These records must also be available for inspection by Comcare.

Regulation 44:  A person conducting a business or undertaking must not use, or direct or allow a worker to use, specific equipment on asbestos or ACM unless the use of the equipment is controlled.

High-pressure water spray and compressed air must not be used on asbestos or ACM. However, high-pressure water spray can be used for fire fighting or fire protection. Power tools, brooms and any other equipment or tool that may release airborne asbestos in the workplace may only be used if it is controlled by it being:

A combination of the controls mentioned above may be required to ensure that airborne asbestos is not generated.

Refer to Section 7.4 of this Code for further information on tools and equipment.


7. CONTROLLING THE RISKS

As mentioned in Chapter 3 of this Code, to eliminate risk of exposure, or if this is not reasonably practicable, minimising them so far as is reasonably practicable, a risk management process should be followed that involves identifying whether asbestos or ACM is at a workplace and including them in the asbestos register, assessing the risk of exposure and then implementing appropriate control measures.

When choosing the most appropriate control measure, the following hierarchy of controls must be considered:

A combination of these controls may be required in order to adequately manage and control asbestos or ACM.

The ultimate goal is to have a workplace free from asbestos. Removal may be the most appropriate way to achieve this. For example:

Specific instances where removal may be the best control measure include:

The Code of Practice: How to Safely Remove Asbestos provides detailed guidance on appropriate work methods and additional controls for the removal of asbestos.

If it is not reasonably practicable to remove asbestos, then other control measures must be implemented to ensure people are not exposed to airborne asbestos, including either enclosing or sealing the asbestos.

Where it is not reasonably practicable to remove asbestos, the preferred alternative control measure is enclosure.  

This may be determined during the risk assessment by reviewing a range of issues including productivity, the condition of the asbestos, the risk it poses to health and cost. This is an interim control measure and should be supported through regular inspections by a competent person to identify if the asbestos requires removal due to damage or deterioration.

Enclosure is the creation of a structure built around the asbestos so that it is completely covered to prevent exposure of the asbestos to air and other substances. Enclosure creates a separate physical barrier that prevents access to the asbestos and therefore minimises the potential for exposure to airborne fibres. Enclosure should only be used on non-friable asbestos where removal is not reasonably practical and where the asbestos is at risk of damage from work activities. Consideration must be given when designing the enclosure for the need to provide access to the asbestos for regular inspection of its condition.


Example of enclosure of asbestos as a control measure:

A large dockside warehouse used for temporarily storing quantities of grain and stockfeed has walls made from a variety of materials, including AC sheet. Apart from the driver of a large frontend loader that is briefly driven into the warehouse to load or unload the feed, there are no other workers who work in the warehouse. An inspection of the AC sheet identifies that it is in good condition and noted that areas of previous minor damage (broken sheets) have been repaired appropriately and there is minimal risk of fibre release. However, it is decided there is a chance the sheets may be damaged again and if so, a risk to health may occur if fibres are released. A solid false wall is constructed to enclose the AC sheet and bollards are erected in front of the new wall to prevent collisions that may occur when the front-end loader is operating inside the warehouse. These changes are included in the asbestos register. The condition of the AC sheet is also monitored as well as the newly installed control measure.

If the asbestos cannot be removed or enclosed, encapsulation or sealing is the next appropriate control measure. For example, if the asbestos is weathered, damaged or broken, it should be removed.

Asbestos that is encapsulated in a resilient matrix, for example in reinforced plastics, vinyls, resins, mastics, bitumen, flexible plasters and cements have little opportunity to release airborne asbestos unless the matrix is damaged. This type of encapsulation will seal any loose fibres into place and should be used only when the original asbestos bond is still intact. Although encapsulation has limited application and can create a health risk for workers undertaking the activity, it is used when it would create a greater risk to remove the asbestos.

Encapsulation helps protect the asbestos from mechanical damage, increases the length of serviceability of the product and may also be used to prevent the release of airborne asbestos during the removal process.  

If encapsulation is recommended, the person carrying out the work should:

Sealing is the process of covering the surface of the material with a protective coating over the asbestos to prevent exposure to airborne asbestos. Sealing asbestos is the least effective method for controlling the release of airborne asbestos. It should only be considered as an interim control while a more effective control such as removing or enclosing can be implemented. It is commonly used for pipe, furnace and boiler insulation. The process either coats the material, reducing fibre release, or binds the fibres together. Asbestos should be sealed, coated or painted to protect it. Sealing is inappropriate where the sealed material is likely to suffer mechanical damage (for example, drilling or sanding).

It is important to select coating that is appropriate to the material to be sealed and has the required fire resistance, thermal insulation and ultraviolet (UV) properties necessary for it to be an effective control. The coating will deteriorate if it is exposed to chemicals, extreme heat or cold, wet or dry conditions or physical impacts. For example, epoxy-based paints offer better durability and strength than other paints.

Under no circumstances should asbestos be water blasted or dry sanded in preparation for painting, coating or sealing, as there is no system of use that can effectively capture or suppress asbestos fibres in such circumstances. To treat asbestos, a method should be used that does not disturb the asbestos.

An airless sprayer at low pressure is preferred to rollers or brushes on exposed (or unsealed) asbestos, as rollers and brushes may cause abrasion/damage and result in fibres being released from the surface of the material. When using a spray brush, never use a high-pressure spray to apply the paint. You should apply it with a dry airless spray using a low pressure to avoid generating high levels of asbestos dust. Several coatings may be needed for full protection.

The surface on which the sealant is to be applied should be cleaned with an asbestos vacuum cleaner fitted with a high efficiency particulate air (HEPA) filter. This will help capture any loose dust or debris from the surface and ensure good adhesion of the sealant. The surface during application should not be disturbed as this releases asbestos dust.

The use of sealants of a different colour to the asbestos being sprayed is helpful in identifying its condition over time and when conducting reviews of the asbestos register. A date-stamped photograph of the sealed surface is also a good way of assisting in the recording of condition.

Example of sealing asbestos as a control measure:

The extensive water pipe system in a large industrial workplace consists of AC piping and conduits. Some of the pipes are located underground, some within inaccessible areas such as walls, and others run aboveground throughout the workplace and are exposed. Connected to some of these pipes in the workplace are control valves that need to be accessed occasionally. Over time, as some of the AC pipes have deteriorated or been damaged, and where practicable to do so, sections of pipe have been removed to reduce the risk. Where a risk still remained, the pipes are enclosed so far as is reasonably practicable to reduce the risk further. Where control valves were connected and the AC pipe was in good condition, it was determined that it was not practicable to remove the asbestos due to lack of available replacement parts, nor was it practicable to enclose the asbestos because access was occasionally required. In this case, sealing the surface of the AC pipes near control valves with an epoxy-based paint to protect the material from deterioration and reduce the risk of airborne asbestos fibres was an appropriate option.

As mentioned in Section 6.4 of this Code, certain equipment must not be used on asbestos. It is therefore important to select the correct equipment to minimise the generation of airborne asbestos.

Manually operated (non-powered) hand tools should be used wherever possible. If they will not provide sufficient physical force to perform the required operation, low-speed, battery-powered tools that are able to be used in conjunction with wet methods for dust control are preferred.

Battery-powered tools should be fitted with a Local Exhaust Ventilation (LEV) dust control hood wherever possible. If an LEV dust control hood cannot be attached and other dust control methodsincluding pastes and gelsare unsuitable, then shadow vacuuming techniques should be used.

Where power tools with dust suppression/extraction are used, exposure monitoring should be carried out to ensure the controls used are effective in reducing the generation of fibres. It is good practice to ensure that the levels of airborne fibres do not exceed one half of the exposure standard (0.1 fibres/ml). If more than half the exposure standard is exceeded, work should be stopped and improvements made to the controls being used.

The use of high-pressure water and compressed air is prohibited under the WHS Regulations as they can cause asbestos to become friable.

Asbestos vacuum cleaners should comply with the requirements in AS/NZS 60335.2.69:2003 Household and similar electrical: Particular requirements for wet and dry vacuum cleaners, including power brush, for industrial and commercial use (IEC 60335-2-69 Ed 3.2 MOD).

Household vacuum cleaners must never be used where asbestos is or may be present, even if they have a HEPA filter.

More comprehensive information about asbestos vacuum cleaners is provided in the Code of Practice: How to Safely Remove Asbestos.

It is important that safe work practices are in place when carrying out asbestos work or asbestos-related work. Wherever possible, dry asbestos should not be worked on. Techniques that prevent or minimise the generation of airborne asbestos fibres include:

When selecting the best technique, the work should first be assessed for any electrical hazards that might result from the use of water or other liquids. If an electrical hazard exists, primary consideration should be given to removing the asbestos, rather than relying on dry work methods.

If asbestos-related work or maintenance or service tasks are assessed by a competent person as involving similar levels of risk, they too may be performed only after the risks for that task have been assessed and appropriate control measures implemented.

The use of high-speed abrasive power and pneumatic tools, including angle grinders, sanders and saws, and high-speed drills, is prohibited under the WHS Regulations, except where used with dust suppression/extraction controls. These controls include local exhaust ventilation (LEV) dust control hoods that attach to the tool and isolate the area being worked on (drilled, sanded etc.) from the environment, ensuring that the dust is captured.

Appendix F outlines examples of safe work practices of service and maintenance tasks that are likely to disturb asbestos and control measures that have been implemented to eliminate or minimise exposure to airborne asbestos.

PPE will need to be used, in combination with other effective control measures, when working with asbestos. The selection and use of PPE should be based on a risk assessment.

If work with asbestos requires the use of other chemicals that are themselves hazardous chemicals, a further risk assessment must be performed. Safety data sheets (SDS) must be referred to for information on appropriate PPE to use and any other precautions to take when using the chemicals (the manufacturer or importer of a hazardous chemical must supply an SDS on request).

The ease of decontamination should be one of the factors considered when choosing PPE.

For PPE that is not clothing and cannot be disposed of, it must be decontaminated and kept in a sealed container until it is reused for the purposes of asbestos-related work.

Further information on decontamination and asbestos waste disposal is available in the Code of Practice: How to Safely Remove Asbestos.

Disposable coveralls should be used as protective clothing unless it is not reasonably practicable to do so. When non-disposable protective clothing is used, the contaminated clothing must be laundered in a suitable laundering facility that is equipped to launder asbestos-contaminated clothing. Contaminated protective clothing must not be laundered in homes. Any clothing worn under coveralls must be disposed of or suitably bagged for laundering as asbestos-contaminated clothing. 

The laundering facility that is equipped to launder asbestos-contaminated clothing:

The contaminated clothing should:

At the laundry facility:

Following any asbestos work carried out, there are requirements to ensure the work area, tools and workers are decontaminated and asbestos waste is disposed of properly. In addition to this, for licensed removal work a clearance certificate will be required before the work area can be reoccupied for ordinary use.  

The Code of Practice: How to Safely Remove Asbestos provides details on decontamination and waste disposal.


APPENDIX A – SAMPLING PROCESS

A competent person should take the following steps to carry out sampling:


APPENDIX B – EXAMPLES OF WARNING SIGNS AND LABELS

EXAMPLES OF WARNING SIGNS AND LABELS - Asbestos waste, do not inhale dust, may cause lung cancer

 

APPENDIX C – TEMPLATE OF AN ASBESTOS REGISTER

 

ASBESTOS REGISTER

Workplace address:

Name of Competent Person:

Date of Identification

Type of Asbestos

Is it Friable or Non-Friable?

Condition of Asbestos

Specific Location of Asbestos

Is this an inaccessible area?

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


APPENDIX D – EXAMPLE OF AN ASBESTOS REGISTER

 

ASBESTOS REGISTER

Workplace address:

 XYZ Manufacturing

 Unit 3A, Trading Estate West, Anytown 9001

Name of Competent Person:

Jim Smith, Site OHS manager (01) 3293 4012

Date of Identification

Type of Asbestos

Is it Friable or Non-Friable?

Condition of Asbestos

Specific Location of Asbestos

Is this an inaccessible area?

1/2/2011

AC Roof Sheeting

Non-friable

Good, minor deterioration on Western End

Whole Roof to main building

Not routinely accessed

1/2/2011

Fibro Wall Cladding

Non-friable

Sound condition structurally, paint lifting in some places

Exterior of main Building

Accessible. Unlikely to be damaged.

1/2/2011

Pipe Insulation

Friable

Cracked at bends in pipe

Plant Room: Behind boiler for water system 

Only accessed by maintenance staff

1/2/2011

Cement Flue

Non-friable

Good condition, coated

Plant Room: On top of boiler

Only accessed by maintenance staff

1/2/2011

Floor Tiles

Non-friable

Good condition, tiles under filing cabinet starting to lift

Main office, Asbestos backed vinyl floor tiles

Inaccessible

 

APPENDIX E – EXAMPLE OF ASBESTOS-RELATED WORK

The risk of exposure to significant amounts of dust that contains asbestos fibres may exist while removing and repairing brakes, clutches and high-temperature gaskets on motor vehicles.

If the following simple controls are applied carefully, it generally should not be necessary to carry out air monitoring in the workshop while servicing vehicle brakes, clutches and cylinder head/exhaust gaskets.

A HEPA-filter industrial vacuum cleaner should be certified by the manufacturer as fit for removal work and can be used to clean all asbestos dust from components and other parts in the immediate vicinity. It may be necessary to purchase or fabricate special hose nozzles to reach difficult areas to ensure components are effectively cleaned of asbestos. Any remaining dust needs to be removed with a wet rag.

A fine spray of water on the dust will dampen it and prevent it being dispersed. The component and parts in the immediate vicinity can then be wiped down with a wet rag. The rag can only be used once. It then needs to be placed in a plastic bag and into an asbestos waste disposal bin. Any spillage onto the workshop floor needs to be wiped up and disposed of in the same way. It is important that only a gentle misting spray is used as a coarse spray will disperse the asbestos fibres into the air.

A respirator certified by the manufacturer as suitable for asbestos dust (for example, a P1 or P2 disposable respirator) needs to be worn during the above cleaning processes.

Compressed air, water hoses and aerosol cans must not be used to clean asbestos dust off components in the open workshop as they will disperse large numbers of fibres into the air.

Personal decontamination should be carried out in accordance with the WHS Regulations and this Code.

To minimise risks to other people, the area where asbestos components are cleaned and removed needs to be segregated and in a location where wind or cooling fans etc. will not disturb any dust. All workers must be provided with information and training on asbestos hazards, its presence and the safety procedures that must be followed.


For all removal:

The process of removing asbestos-containing linings from brake shoes and clutch parts has the potential to release large quantities of asbestos fibres. All work involving power tools should be carried out within an enclosure that is fitted with an effective dust extraction and filtration system that will eliminate or minimise the release of airborne asbestos fibres. If components are to be hand-worked, carry out the following procedure:


APPENDIX F – RECOMMENDED SAFE WORKING PRACTICES

 

As a first priority, planning for the maintenance of asbestos at the workplace must include consideration of the removal of the asbestos as the most preferred control option. Where removed, products containing asbestos must be replaced with products that do not contain asbestos. Removal of asbestos products must be done in accordance with the Code of Practice: How to Safely Remove Asbestos.

 

Below are some recommended safe working methods that demonstrate how control measures can be used when asbestos is present at the workplace: 

 


SAFE WORK PRACTICE 1 DRILLING OF ACM

The drilling of asbestos cement sheeting can release asbestos fibres into the atmosphere, so precautions must be taken to protect the drill operator and other persons from exposure to these fibres. A hand drill is preferred to a battery-powered drill, because the quantity of fibres is drastically reduced if a hand drill is used.

Equipment that may be required prior to starting work (in addition to what is needed  for the task)

  • A non-powered hand drill or a low-speed battery-powered drill or drilling equipment. Battery-powered drills should be fitted with a local exhaust ventilation (LEV) dust control hood wherever possible. If an LEV dust control hood cannot be attached and other dust control methods such as pastes and gels are unsuitable then shadow vacuuming techniques should be used
  • Disposable cleaning rags
  • A bucket of water, or more as appropriate, and/or a misting spray bottle
  • Duct tape
  • Sealant
  • Spare PPE
  • A thickened substance such as wallpaper paste, shaving cream or hair gel
  • 200 µm plastic sheeting
  • A suitable asbestos waste container (e.g. 200 µm plastic bags or a drum, bin or skip lined with 200 µm plastic sheeting)
  • Warning signs and/or barrier tape
  • An asbestos vacuum cleaner
  • A sturdy paper, foam or thin metal cup, or similar (for work on overhead surfaces only).

PPE

  • Protective clothing and RPE (see AS1715, AS 1716). It is likely that a class P1 or P2 half face respirator will be adequate for this task, provided the recommended safe work procedure is followed.

Preparing the asbestos work area

 

  • If the work is to be carried out at a height, appropriate precautions must be taken to prevent falls.
  • Ensure appropriately marked asbestos waste disposal bags are available.
  • Carry out the work with as few people present as possible.
  • Segregate the asbestos work area to ensure unauthorised personnel are restricted from entry (e.g. close door and/or use warning signs and/or barrier tape at all entry points). The distance for segregation should be determined by a risk assessment.
  • If drilling a roof from outside, segregate the area below.
  • If access is available to the rear of the asbestos cement, segregate this area as well as above.
  • If possible, use plastic sheeting, secured with duct tape, to cover any surface within the asbestos work area that could become contaminated.
  • Ensure there is adequate lighting.
  • Avoid working in windy environments where asbestos fibres can be redistributed.
  • If using a bucket of water, do not resoak used rags in the bucket, as this will contaminate the water. Instead, either fold the rag so a clean surface is exposed or use another rag.

Drilling vertical surfaces

  • Tape both the point to be drilled and the exit point, if accessible, with a strong adhesive tape such as duct tape to prevent the edges crumbling.
  • Cover the drill entry and exit points (if accessible) on the asbestos with a generous amount of thickened substance.
  • Drill through the paste.
  • Use damp rags to clean off the paste and debris from the wall and drill bit.
  • Dispose of the rags as asbestos waste as they will contain asbestos dust and fibres.
  • Seal the cut edges with sealant.
  • If a cable is to be passed through, insert a sleeve to protect the inner edge of the hole.

Drilling overhead horizontal surfaces

  • Mark the point to be drilled.
  • Drill a hole through the bottom of the cup.
  • Fill or line the inside of the cup with shaving cream, gel or a similar thickened substance.
  • Put the drill bit through the hole in the cup so that the cup encloses the drill bit, and make sure the drill bit extends beyond the lip of the cup.
  • Align the drill bit with the marked point.
  • Ensure the cup is firmly held against the surface to be drilled.
  • Drill through the surface.
  • Remove the drill bit from the cup, ensuring that the cup remains firmly against the surface.
  • Remove the cup from the surface.
  • Use damp rags to clean off the paste and debris from the drill bit.
  • Dispose of the rags as asbestos waste, as they will contain asbestos dust and fibres.
  • Seal the cut edges with sealant.
  • If a cable is to be passed through, insert a sleeve to protect the inner edge of the hole.

Decontaminating the asbestos work area and equipment

  • Use damp rags to clean the equipment.
  • Carefully roll or fold any plastic sheeting used to cover any surface within the asbestos work area, so as not to spill any dust or debris that has been collected.
  • If necessary, use damp rags and/or an asbestos vacuum cleaner to clean any remaining visibly contaminated sections of the asbestos work area.
  • Place debris, used rags, plastic sheeting and other waste in the asbestos waste bags/container.
  • Wet wipe the external surfaces of the asbestos waste bags/container to remove any adhering dust before they are removed from the asbestos work area.

Personal decontamination should be carried out in a designated area

  • If disposable coveralls are worn, clean the coveralls while still wearing RPE using a HEPA vacuum, damp rag or fine-water spray. RPE can be cleaned with a wet rag or cloth.
  • While still wearing RPE, remove coveralls, turning them inside-out to entrap any remaining contamination and then place them into a labelled asbestos waste bag.
  • Remove RPE. If non-disposable, inspect it to ensure it is free from contamination, clean it with a wet rag and store in a clean container. If disposable, cleaning is not required but RPE should be placed in a labelled asbestos waste bag or waste container.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

Clearance procedure

  • Visually inspect the asbestos work area to make sure it has been properly cleaned.
  • Clearance air monitoring is not normally required for this task.
  • Dispose of all waste as asbestos waste.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

 

 

SAFE WORK PRACTICE 2 SEALING, PAINTING, COATING AND CLEANING OF ASBESTOS-CEMENT PRODUCTS

These tasks should only to be carried out on asbestos that are in good condition. For this reason, the ACM should be thoroughly inspected before starting the work. There is a risk to health if the surface of asbestos cement sheeting is disturbed (e.g. from hail storms and cyclones) or if it has deteriorated as a result of aggressive environmental factors such as pollution. If it is so weathered that its surface is cracked or broken, the asbestos cement matrix may be eroded, increasing the likelihood that asbestos fibres will be released. If treatment is considered essential, a method that does not disturb the matrix should be used. Under no circumstances should asbestos cement products be water blasted or dry sanded in preparation for painting, coating or sealing.

Equipment that may be required prior to starting work (in addition to what is needed  for the task)

  • Disposable cleaning rags
  • A bucket of water, or more as appropriate, and/or a misting spray bottle
  • Sealant
  • Spare PPE
  • A suitable asbestos waste container
  • Warning signs and/or barrier tape.

PPE

  • Protective clothing and RPE (see AS1715, AS 1716). It is likely that a class P1 or P2 half face respirator will be adequate for this task, provided the recommended safe work procedure is followed. Where paint is to be applied, appropriate respiratory protection to control the paint vapours/mist must also be considered.

Preparing the asbestos work area

 

  • If work is being carried out at heights, precautions must be taken to prevent falls.
  • Before starting, assess the asbestos cement for damage.
  • Ensure appropriately marked asbestos waste disposal bags are available.
  • Carry out the work with as few people present as possible.
  • Segregate the asbestos work area to ensure unauthorised personnel are restricted from entry (e.g. close door and/or use warning signs and/or barrier tape at all entry points). The distance for segregation should be determined by a risk assessment.
  • If working at a height, segregate the area below.
  • If possible, use plastic sheeting secured with duct tape to cover any floor surface within the asbestos work area which could become contaminated. This will help to contain any runoff from wet sanding methods.
  • Ensure there is adequate lighting.
  • If using a bucket of water, do not resoak used rags in the bucket, as this will contaminate the water. Instead, either fold the rag so a clean surface is exposed or use another rag.
  • Never use high-pressure water cleaning methods.
  • Never prepare surfaces using dry sanding methods. Where sanding is required, you should consider removing the asbestos and replacing it with a non-asbestos product.
  • Wet sanding methods may be used to prepare the asbestos, provided precautions are taken to ensure all the runoff is captured and filtered, where possible.
  • Wipe dusty surfaces with a damp cloth.

Painting and sealing

  • When using a spray brush, never use a high-pressure spray to apply the paint.
  • When using a roller, use it lightly to avoid abrasion or other damage.

Decontaminating the asbestos work area and equipment

  • Use damp rags to clean the equipment.
  • If required, use damp rags and/or an asbestos vacuum cleaner to clean the asbestos work area.
  • Place debris, used rags, plastic sheeting and other waste in the asbestos waste bags/container.
  • Wet wipe the external surfaces of the asbestos waste bags/container to remove any adhering dust before they are removed from the asbestos work area.

Personal decontamination should be carried out in a designated area

  • If disposable coveralls are worn, clean the coveralls while still wearing RPE using a HEPA vacuum, damp rag or fine-water spray. RPE can be cleaned with a wet rag or cloth.
  • While still wearing RPE, remove coveralls, turning them inside-out to entrap any remaining contamination and then place them into a labelled asbestos waste bag.
  • Remove RPE. If non-disposable, inspect it to ensure it is free from contamination, clean it with a wet rag and store in a clean container. If disposable, cleaning is not required but RPE should be placed in a labelled asbestos waste bag or waste container.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

Clearance procedure

  • Visually inspect the asbestos work area to make sure it has been properly cleaned.
  • Clearance air monitoring is not normally required for this task.
  • Dispose of all waste as asbestos waste.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

 

 

SAFE WORK PRACTICE 3 CLEANING LEAF LITTER FROM GUTTERS OF ASBESTOS CEMENT ROOFS

Equipment that may be required prior to starting work (in addition to what is needed  for the task)

  • A bucket of water, or more as appropriate, and detergent
  • A watering can or garden spray
  • A hand trowel or scoop
  • Disposable cleaning rags
  • A suitable asbestos waste container
  • Warning signs and/or barrier tape
  • An asbestos vacuum cleaner.

PPE

  • Protective clothing and RPE (see AS1715, AS 1716). It is likely that a class P1 or P2 half face respirator will be adequate for this task, provided the recommended safe work procedure is followed.

Preparing the asbestos work area

 

  • Since the work is to be carried out at a height, appropriate precautions must be taken to prevent the risk of falls.
  • Ensure appropriately marked asbestos waste disposal containers are available.
  • Segregate the asbestos work area to ensure unauthorised personnel are restricted from entry (e.g. use warning signs and/or barrier tape at all entry points). The distance for segregation should be determined by a risk assessment.
  • Segregate the area below.
  • Avoid working in windy environments where asbestos fibres can be redistributed.
  • If using a bucket of water, do not resoak used rags in the bucket as this will contaminate the water. Instead, either fold the rag so a clean surface is exposed or use another rag.

Gutter cleaning

  • Disconnect or re-route the downpipes to prevent any entry of contaminated water into the waste water system and ensure there is a suitable container to collect contaminated runoff. Contaminated water must be disposed of as asbestos waste.
  • Mix the water and detergent.
  • Using the watering can or garden spray, pour the water and detergent mixture into the gutter but avoid over-wetting as this will create a slurry.
  • Remove the debris using a scoop or trowel. Do not allow debris or slurry to enter the water system.
  • Wet the debris again if dry material is uncovered.
  • Place the removed debris straight into the asbestos waste container.

Decontaminating the asbestos work area and equipment

  • Use damp rags to wipe down all equipment used.
  • Use damp rags to wipe down the guttering.
  • Where practicable, and if necessary, use an asbestos vacuum cleaner to vacuum the area below.
  • Place debris, used rags and other waste in the asbestos waste container.
  • Wet wipe the external surfaces of the asbestos waste container to remove any adhering dust before it is removed from the asbestos work area.

Personal decontamination should be carried out in a designated area

  • If disposable coveralls are worn, clean the coveralls while still wearing RPE using a HEPA vacuum, damp rag or fine-water spray. RPE can be cleaned with a wet rag or cloth.
  • While still wearing RPE, remove coveralls, turning them inside-out to entrap any remaining contamination and then place them into a labelled asbestos waste bag.
  • Remove RPE. If non-disposable, inspect it to ensure it is free from contamination, clean it with a wet rag and store in a clean container. If disposable, cleaning is not required but RPE should be placed in a labelled asbestos waste bag or waste container.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

Clearance procedure

  • Visually inspect the asbestos work area to make sure it has been properly cleaned.
  • Clearance air monitoring is not normally required for this task.
  • Dispose of all waste as asbestos waste.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

 

 

SAFE WORK PRACTICE 4 REPLACE CABLING IN ASBESTOS CEMENT CONDUITS OR BOXES

Equipment that may be required prior to starting the work (in addition to what is required  for the task)

  • Disposable cleaning rags
  • A bucket of water, or more as appropriate, and/or a misting spray bottle
  • 200 µm thick plastic sheeting
  • Cable slipping compound
  • Appropriately marked asbestos waste disposal bags
  • Spare PPE
  • Duct tape
  • Warning signs and/or barrier tape
  • An asbestos vacuum cleaner.

PPE

  • Protective clothing and RPE (see AS1715, AS 1716). It is likely that a class P1 or P2 half face respirator will be adequate for this task, provided the recommended safe work procedure is followed.

Preparing the asbestos work area

 

  • If the work will be carried out in a confined space, appropriate precautions must be taken to prevent the risk of asphyxiation.
  • Ensure appropriately marked asbestos waste disposal bags are available.
  • Carry out the work with as few people present as possible.
  • Segregate the asbestos work area to ensure unauthorised personnel are restricted from entry (e.g. use warning signs and/or barrier tape at all entry points). The distance for segregation should be determined by a risk assessment.
  • Use plastic sheeting secured with duct tape to cover any surface within the asbestos work area which could become contaminated.
  • Place plastic sheeting below any conduits before pulling any cables through.
  • Ensure there is adequate lighting.
  • Avoid working in windy environments where asbestos fibres can be redistributed.
  • If using a bucket of water, do not resoak used rags in the bucket as this will contaminate the water. Instead, either fold the rag so a clean surface is exposed or use another rag.

Replacement or installation of cables

  • Wet down the equipment and apply adequate cable slipping compound to the conduits/ducts throughout the process.
  • Clean all ropes, rods or snakes used to pull cables after use. Cleaning should be undertaken close to the point(s) where the cables exit from the conduits/ducts.
  • Ropes used for cable pulling should have a smooth surface that can easily be cleaned.
  • Do not use metal stockings when pulling cables through asbestos cement conduits.
  • Do not use compressed air darts to pull cables through asbestos cement conduits/ducts.

Decontaminating the asbestos work area and equipment

  • Use damp rags to clean the equipment.
  • Wet wipe around the end of the conduit, sections of exposed cable and the pulling eye at the completion of the cable pulling operation.
  • If the rope or cable passes through any rollers, these must also be wet wiped after use.
  • Wet wipe the external surface of excess cable pulled through the conduit/duct, as close as possible to the exit point from the conduit, before it is removed from the work site.
  • Carefully roll or fold any plastic sheeting used to cover any surface within the asbestos work area, so as not to spill any dust or debris that has been collected.
  • If required, use damp rags or an asbestos vacuum cleaner to clean any remaining visibly contaminated sections of the asbestos work area.
  • Place all debris, used rags, plastic sheeting and other waste in the asbestos waste bags/container.
  • Wet wipe the external surfaces of the asbestos waste bags/container to remove any adhering dust before they are removed from the asbestos work area.

Personal decontamination should be carried out in a designated area

  • If disposable coveralls are worn, clean the coveralls while still wearing RPE using a HEPA vacuum, damp rag or fine-water spray. RPE can be cleaned with a wet rag or cloth.
  • While still wearing RPE, remove coveralls, turning them inside-out to entrap any remaining contamination and then place them into a labelled asbestos waste bag.
  • Remove RPE. If non-disposable, inspect it to ensure it is free from contamination, clean it with a wet rag and store in a clean container. If disposable, cleaning is not required but RPE should be placed in a labelled asbestos waste bag or waste container.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

Clearance procedure

  • Visually inspect the asbestos work area to make sure it has been properly cleaned.
  • Clearance air monitoring is not normally required for this task.
  • Dispose of all waste as asbestos waste.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

 

 

SAFE WORK PRACTICE 5 WORKING ON ELECTRICAL MOUNTING BOARDS CONTAINING ASBESTOS

If the asbestos-containing electrical mounting panel has to be removed for work behind the board, the procedures outlined in the Code of Practice: How to Safely Remove Asbestos must be followed. If drilling is required, the control process should be consistent with the measures in Safe Work Practice 1.

Equipment that may be required prior to starting the work (in addition to what is required  for the task)

  • A non-powered hand drill or a low-speed battery-powered drill or drilling equipment. Battery-powered drills should be fitted with a LEV dust control hood wherever possible. If a LEV dust control hood cannot be attached and other dust control methods, such as pastes and gels, are unsuitable then shadow vacuuming techniques should be used
  • Duct tape
  • Warning signs and/or barrier tape
  • Disposable cleaning rags
  • A plastic bucket of water and/or a misting spray bottle
  • Spare PPE
  • A suitable asbestos waste container
  • 200 mm plastic sheeting
  • An asbestos vacuum cleaner.

PPE

  • Protective clothing and RPE (see AS1715, AS 1716. It is likely that a class P1 or P2 half face respirator will be adequate for this task, provided the recommended safe work procedure is followed.

Preparing the asbestos work area

 

  • As the work area will involve electrical hazards, precautions must be taken to prevent electrocution.
  • Ensure appropriately marked asbestos waste disposal bags are available.
  • Carry out the work with as few people present as possible.
  • Segregate the asbestos work area to ensure unauthorised personnel are restricted from entry (e.g. use warning signs and/or barrier tape at all entry points). The distance for segregation should be determined by a risk assessment.
  • Use plastic sheeting secured with duct tape to cover any surface within the asbestos work area which could become contaminated.
  • Ensure there is adequate lighting.
  • Avoid working in windy environments where asbestos fibres can be redistributed.
  • If using a bucket of water, do not resoak used rags in the bucket as this will contaminate the water. Instead, either fold the rag so a clean surface is exposed or use another rag.

Work on electrical mounting panels

  • Providing the panel is not friable, maintenance and service work may include:
  • replacing asbestos containing equipment on the electrical panel with non-asbestos equipment
  • operate main switches and individual circuit devices
  • pull/insert service and circuit fuses
  • bridge supplies at meter bases
  • use testing equipment
  • access the neutral link
  • install new components/equipment.

Decontaminating the asbestos work area and equipment

  • Use damp rags to clean the equipment.
  • Carefully roll or fold any plastic sheeting used to cover any surface within the asbestos work area so as not to spill any dust or debris that has been collected.
  • If there is an electrical hazard, use an asbestos vacuum cleaner to remove any dust from the mounting panel and other visibly contaminated sections of the asbestos work area.
  • If there is no electrical hazard, wet wipe with a damp rag to remove minor amounts of dust.
  • Place debris, used rags, plastic sheeting and other waste in the asbestos waste bags/container.
  • Wet wipe the external surfaces of the asbestos waste bags/container to remove any adhering dust before they are removed from the asbestos work area.

Personal decontamination should be carried out in a designated area

  • If disposable coveralls are worn, clean the coveralls while still wearing RPE using a HEPA vacuum, damp rag or fine-water spray. RPE can be cleaned with a wet rag or cloth.
  • While still wearing RPE, remove coveralls, turning them inside-out to entrap any remaining contamination and then place them into a labelled asbestos waste bag.
  • Remove RPE. If non-disposable, inspect it to ensure it is free from contamination, clean it with a wet rag and store in a clean container. If disposable, cleaning is not required but RPE should be placed in a labelled asbestos waste bag or waste container.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

Clearance procedure

  • Visually inspect the asbestos work area to make sure it has been properly cleaned.
  • Clearance air monitoring is not normally required for this task.
  • Dispose of all waste as asbestos waste.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

 

 

SAFE WORK PRACTICE 6 INSPECTION OF ASBESTOS FRICTION MATERIALS

This guide may be used when friction ACM (e.g. brake assemblies or clutch housings) need to be inspected or housings need to be cleaned. Compressed air must not be used to clean dust from a brake assembly.

Equipment that may be required prior to starting the work (in addition to what is required  for the task)

  • A misting spray bottle
  • Duct tape
  • Warning signs and/or barrier tape
  • Disposable cleaning rags
  • A bucket of water and detergent
  • Spare PPE
  • A suitable asbestos waste container
  • A catch tray or similar container
  • An asbestos vacuum cleaner.

PPE

  • Protective clothing and RPE (see AS1715, AS 1716). It is likely that a class P1 or P2 half face respirator will be adequate for this task, provided the recommended safe work procedure is followed.

Preparing the asbestos work area

 

  • Ensure appropriately marked asbestos waste disposal bags are available.
  • Carry out the work with as few people present as possible.
  • Determine whether to segregate the asbestos work area 
  • Ensure unauthorised personnel are restricted from entry by using barrier tape and/or warning signs.
  • Use a suitable collection device below where the work will be carried out to collect any debris/ runoff.
  • Ensure there is adequate lighting.
  • Avoid working in windy environments where asbestos fibres can be redistributed.
  • If using a bucket of water, do not resoak used rags in the bucket as this will contaminate the water. Instead, either fold the rag so a clean surface is exposed or use another rag.

Inspection of asbestos friction materials

  • A misting spray bottle should be used to wet down any dust. If spray equipment disturbs asbestos, use alternative wetting agents e.g. a water-miscible degreaser or a water/detergent mixture.
  • Use the wet method, but if this is not possible the dry method may then be used.

Wet method:

  • Use the misting spray bottle to wet down any visible dust.
  • Use a damp rag to wipe down the wheel or automobile part before removal. Ensure the dust is kept wet to prevent atmospheric contamination.
  • Use hand tools rather than power tools to reduce the generation of airborne fibres.
  • Partially open the housing and softly spray the inside with water using the misting spray bottle. Any spillage of dust, debris or water must be controlled (e.g. capturing any runoff in a container) and either filtered or disposed of as asbestos waste.
  • Open the housing and clean all asbestos parts using a damp rag, ensuring all runoff water is caught in an asbestos waste container.

 

 

Dry method:

  • Place a tray under the components to catch dust or debris spilling from the housing or components during the inspection and dispose of any material as asbestos waste.
  • Use an asbestos vacuum cleaner to remove asbestos from the brakes and rims or other materials before carrying out the inspection.

Decontaminating the asbestos work area and equipment

  • Use damp rags to clean the equipment, including the dust collection tray.
  • If necessary, use damp rags or an asbestos vacuum cleaner to clean any remaining visibly contaminated sections of the asbestos work area.
  • Place debris, used rags and other waste in the asbestos waste bags/container.
  • Wet wipe the external surfaces of the asbestos waste bags/container to remove any adhering dust before removing them from the asbestos work area.

Personal decontamination should be carried out in a designated area

  • If disposable coveralls are worn, clean the coveralls and RPE while still wearing them using an asbestos vacuum cleaner, damp rag or fine-water spray. RPE can be cleaned with a wet rag/cloth.
  • While still wearing RPE, remove coveralls, turning them inside-out to entrap any remaining contamination and then place them into a labelled asbestos waste bag.
  • Remove RPE. If non-disposable, inspect it to ensure it is free from contamination, clean it with a wet rag and store in a clean container. If disposable, cleaning is not required but RPE should be placed in a labelled asbestos waste bag or waste container.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

Clearance procedure

  • Visually inspect the asbestos work area to make sure it has been properly cleaned.
  • Clearance air monitoring is not normally required for this task.
  • Dispose of all waste as asbestos waste.

Refer to the Code of Practice: How to Safely Remove Asbestos for more information.

 


TABLE OF CONTENTS

 

 

FOREWORD

 

SCOPE AND APPLICATION

1.

INTRODUCTION

1.1 

Who has health and safety duties when removing asbestos?

1.2 

The meaning of key terms

1.3

Licence requirements for asbestos removal work

1.4

Health monitoring duties

2.

DUTIES FOR REMOVAL WORK THAT DOES NOT REQUIRE A LICENCE

2.1 

Training all workers about asbestos or ACM

3.

DUTIES FOR LICENSED ASBESTOS REMOVAL

3.1

Asbestos removalist supervisor to be present or readily available

3.2

Certification and training

3.3

Informing parties of the licensed asbestos removal

3.4

Obtaining the asbestos register

3.5

Preparing an asbestos removal control plan

3.6

Notifying Comcare of the licensed asbestos removal work

3.7

Limiting access, displaying signs and installing barricades

3.8

Decontamination

3.9

Waste containment and disposal

3.10

Clearance inspection

3.11

Air monitoring

3.12

Removing friable asbestos

4.

CONTROLS APPLICABLE TO ALL TYPES OF ASBESTOS REMOVAL

4.1

Identifying hazards

4.2

Indicating the asbestos removal areas

4.3

Wet and dry methods

4.4

Tools and equipment

4.5

Personal protective equipment

4.6

Decontamination

4.7

Laundering clothing

4.8

Waste containment and disposal

5.

USING AN ENCLOSURE DURING LARGE SCALE REMOVAL WORK

5.1

Designing and installing an enclosure

5.2

Testing an enclosure

5.3

Information on pressure exhaust units (negative units)

6.

METHODS FOR SMALL SCALE REMOVAL WORK

6.1

Mini-enclosure

6.2

Glove bag asbestos removal work

6.3

Wrap and cut asbestos removal method

7.

CONTROLS FOR SPECIFIC ASBESTOS REMOVAL WORK

7.1

Removing asbestos-contaminated soil

7.2

Removing friable asbestos from hot surfaces

7.3

Removing asbestos in plan and pipes or pits

 

APPENDIX A – ASBESTOS REMOVAL CONTROL PLAN CONTENTS

 

APPENDIX B  RESPIRATORY PROTECTIVE EQUIPMENT

 

APPENDIX C - EXAMPLE OF A CLEARANCE CERTIFICATE

 

APPENDIX D  EXAMPLES OF ASBESTOS REMOVAL WORK


FOREWORD

This Code of Practice on how to safely remove asbestos is an approved code of practice under section 274 of the Work Health and Safety Act 2011  (the WHS Act).

An approved code of practice is a practical guide to achieving the standards of health, safety and welfare required under the WHS Act and the Work Health and Safety Regulations 2011 (the WHS Regulations).

A code of practice applies to anyone who has a duty of care in the circumstances described in the code. In most cases, following an approved code of practice would achieve compliance with the health and safety duties in the WHS Act, in relation to the subject matter of the code. Like regulations, codes of practice deal with particular issues and do not cover all hazards or risks that may arise. The health and safety duties require duty holders to consider all risks associated with work, not only those for which regulations and codes of practice exist.

Codes of practice are admissible in court proceedings under the WHS Act and Regulations. Courts may regard a code of practice as evidence of what is known about a hazard, risk or control and may rely on the code in determining what is reasonably practicable in the circumstances to which the code relates.

The WHS Act and Regulations may be complied with by following another method, such as a technical or an industry standard, if it provides an equivalent or higher standard of work health and safety than the code.

An inspector may refer to an approved code of practice when issuing an improvement or prohibition notice. 

This Code of Practice is based on the draft code of practice developed by Safe Work Australia as a model code of practice under the Council of Australian Governments’ Inter-Governmental Agreement for Regulatory and Operational Reform in Occupational Health and Safety for adoption by the Commonwealth, state and territory governments.

A draft of that model code of practice was released for public consultation on 7 December 2010 and was endorsed by the Workplace Relations Ministers’ Council on 10 August 2011.


SCOPE AND APPLICATION

This Code of Practice provides practical guidance for persons conducting a business or undertaking who have duties under the WHS Act and WHS Regulations to safely remove asbestos from all workplaces including structures, plant and equipment. 

A person conducting a business or undertaking may be an asbestos removalist who may carry out asbestos removal work that does not require a licence, Class A asbestos removal work or Class B asbestos removal work. This could include both asbestos removal companies and those persons who may carry out small asbestos removal jobs and may not have an asbestos licence, for example tradespersons.

It is recommended that other persons with responsibilityfor example, a person conducting a business or undertaking who commissions removal work at a workplace (person who commissions removal work)should read this Code to ensure they are aware of mandatory requirements.

This Code of Practice may also be used by workers and their health and safety representatives and other persons affected by asbestos removal work, for example neighbours.

It is important to read the Code of Practice: How to Manage and Control Asbestos in the Workplace, as it provides specific guidance on identifying asbestos or asbestos containing material (ACM) in the workplace, determining whether removal is the best control option and implementing other control measures if removing asbestos is not the most appropriate action to take.

Some chapters of this Code will apply to asbestos that is present in domestic premises where the premises becomes a workplace.

In providing guidance, the word ‘should’ is used in this Code of Practice  to indicate a recommended course of action, while ‘may’ is used to indicate an optional course of action.

This Code of Practice also includes various references to provisions of the WHS Act and Regulations to provide context with legal requirements. These references are not exhaustive. The words ‘must’, ‘requires’ or ‘mandatory’ indicate that these legal requirements exist and must be complied with.


1. INTRODUCTION

The WHS Act requires all persons who conduct a business or undertaking to ensure, so far as is reasonably practicable, that workers and other persons are not put at risk from work carried out as part of the business or undertaking.

The person conducting a business or undertaking must also ensure so far as is reasonably practicable that exposure of a person at the workplace to airborne asbestos is eliminated. If this is not reasonably practicable, the exposure must be minimised so far as is reasonably practicable. The exposure standard for asbestos must not be exceeded.

The WHS Regulations include specific obligations for a number of duty holders in relation to safely removing asbestos. These duties are summarised in Chapters 2 and 3 of this Code.

Officers, such as company directors, have a duty to exercise due diligence to ensure that the business or undertaking complies with the WHS Act and WHS Regulations. This includes taking reasonable steps to ensure that the business or undertaking has and uses appropriate resources and processes to eliminate or minimise risks associated with asbestos.

Workers have a duty to take reasonable care for their own health and safety and to not adversely affect the health and safety of other persons. They must comply with any reasonable instruction and cooperate with any reasonable policy or procedure relating to health and safety at the workplace. If personal protective equipment (PPE) is provided by the person conducting the business or undertaking, the worker must use it in accordance with information, instruction and training provided on their use.

There are a number of specific duties in both the WHS Act and WHS Regulations that require consultation with others throughout the asbestos removal process. Communicating and consulting with a range of people helps to increase the awareness of the potential health and safety risks of asbestos.

An asbestos removalist must consult with persons who may be affected by the asbestos removal work, as well as other responsible persons at the workplace, to eliminate or minimise the exposure to the risks associated with asbestos, for example site management or the project manager, workers, health and safety representatives, contractors, building occupants and others. This also includes speaking with neighbours and other businesses where the asbestos removal work is occurring at domestic premises. 

Further guidance on consultation is available in the Code of Practice: Work Health and Safety Consultation, Cooperation and Coordination.

Airborne asbestos means any fibres of asbestos small enough to be made airborne. For the purposes of monitoring airborne asbestos fibres, only respirable fibres are counted.

Asbestos means the asbestiform varieties of mineral silicates belonging to the serpentine or amphibole groups of rock-forming minerals, including actinolite asbestos, grunerite (or amosite) asbestos (brown), anthophyllite asbestos, chrysotile asbestos (white), crocidolite asbestos (blue) and tremolite asbestos.

Asbestos containing material (ACM) means any material or thing that, as part of its design, contains asbestos.

Asbestos-contaminated dust or debris (ACD) means dust or debris that has settled within a workplace and is (or assumed to be) contaminated with asbestos.

Asbestos-related work means work involving asbestos (other than asbestos removal work to which Part 8.7 of the WHS Regulations applies) that is permitted under the exceptions set out in regulation 419(3), (4) and (5).

Asbestos removalist means a person conducting a business or undertaking who carries out asbestos removal work.

Asbestos removal work means:

Competent person in relation to carrying out clearance inspections under regulation 473 means a person who has acquired through training or experience the knowledge and skills of relevant asbestos removal industry practice and holds a certification in relation to the specified VET course for asbestos assessor work or a tertiary qualification in occupational health and safety, occupational hygiene, science, building, construction or environmental health. For all other purposes, competent person means a person who has acquired through training, qualification or experience, the knowledge and skills to carry out the task.

Exposure standard for asbestos is a respirable fibre level of 0.1 fibres/ml of air measured in a person’s breathing zone and expressed as a time weighted average fibre concentration calculated over an eight-hour working day and measured over a minimum period of four hours in accordance with:

Friable asbestos means material that is in a powder form or that can be crumbled, pulverised or reduced to a powder by hand pressure when dry, and contains asbestos.

GHS means Globally Harmonised System of Classification and Labelling of Chemicals, Third revised edition, published by the United Nations as modified under Schedule 6 of the WHS Regulations.

Licensed asbestos assessor means a person who holds an asbestos assessor licence.

Licensed asbestos removalist means a person conducting a business or undertaking who is licensed under the WHS Regulations to carry out asbestos removal work.

Naturally occurring asbestos (NOA) means the natural geological occurrence of asbestos minerals found in association with geological deposits including rock, sediment or soil.

Non-friable asbestos means material containing asbestos that is not friable, including material containing asbestos fibres reinforced with a bonding compound.

Respirable asbestos means an asbestos fibre that:

Regulation 458: The WHS Regulations require a person conducting a business or undertaking who commissions the removal of asbestos at the workplace to ensure asbestos removal work is carried out only by a licensed asbestos removalist who is appropriately licensed to carry out the work, unless specified in the WHS Regulations that a licence is not required.

There are two types of licences: Class A and Class B. The type of licence required will depend on the type and quantity of asbestos or ACM that is being removed at a workplace.


Type of licence

What asbestos can be removed?

Class A

Can remove any amount or quantity of asbestos or ACM, including:

  • any amount of friable asbestos or ACM
  • any amount of ACD
  • any amount of non-friable asbestos or ACM.

Class B

Can remove:

  • any amount of non-friable asbestos or ACM

(Note: A Class B licence is required for removal of more than 10 m2 of nonfriable asbestos or ACM but the licence holder can also remove up to 10 m2 of non-friable asbestos or ACM).

  • ACD associated with the removal of non-friable asbestos or ACM.

(Note: A Class B licence is required for removal of ACD associated with the removal of more than 10 m² of non-friable asbestos or ACM but the licence holder can also remove ACD associated with removal of up to 10m² of nonfriable asbestos or ACM.

No licence required

Can remove:

  • up to 10 m2 of non-friable asbestos or ACM
  • ACD that is:
  • associated with the removal of less than 10 m2 of non-friable asbestos or ACM
  • not associated with the removal of friable or non-friable asbestos and is only a minor contamination.

The WHS Regulations require that a person must hold an asbestos assessor licence to conduct the following:

A licensed assessor can also carry out a number of other tasks including identifying asbestos, carrying out a risk assessment or reviewing an asbestos register.

Regulations 435-444:  The WHS Regulations require a person conducting a business or undertaking to ensure health monitoring is provided to a worker if they are carrying out licensed asbestos removal work, other ongoing asbestos removal work or asbestos-related work and is at risk of exposure to asbestos when carrying out the work.

Health monitoring includes a medical examination to provide an initial baseline medical assessment. The medical examination should be performed in accordance with the Guidance: Health Monitoring [under development].

Health monitoring must include the following (unless another form of health monitoring is recommended by a registered medical practitioner):

 

Workers must be informed of any health monitoring requirements before the worker carries out work that may expose them to asbestos.

Where a worker is at risk of exposure to asbestos due to work other than licensed asbestos removal, health monitoring must also be undertaken. Examples of work where there is a risk of exposure include ongoing unlicensed removal work, undertaking maintenance work on ACM regularly as part of another job (for instance, electricians or building maintenance staff in older buildings) and carrying out asbestos-related work. The need for health monitoring for these workers should be determined on the basis of:

If a worker is carrying out licensed asbestos removal work, the health monitoring must be conducted prior to the worker commencing the work. Health monitoring should also be provided to the worker at regular intervals after commencing the asbestos-related work but at least once every two years.

Health monitoring must be carried out under the supervision of a registered medical practitioner with the relevant competencies. Prior to deciding who the registered medical practitioner will be, the person conducting a business or undertaking must consult the worker.

The person conducting a business or undertaking must pay all expenses relating to health monitoring.

Where there are two or more persons that have a duty to provide health monitoring to a worker, they may choose that one person organises health monitoring (known as the person who commissions the health monitoring), however the costs must be shared equally between each person unless they agree otherwise.

The person who commissions health monitoring must provide the following information to the registered medical practitioner:

A person who commissions health monitoring must take all reasonable steps to obtain a report from the registered medical practitioner as soon as practicable after the monitoring is carried out. 

The health monitoring report must include the following information:

That person must also give a copy of the report, as soon as reasonably possible after obtaining it from the medical practitioner, to:

Reports must be kept as a confidential record for at least 40 years after the record is made and identified as a formal record for the particular worker. The report and results must not be disclosed to anyone unless the worker has provided their written consent. However, if the person was releasing the record under a duty of professional confidentiality, the worker’s written consent is not required.


2. DUTIES FOR REMOVAL WORK THAT DOES NOT REQUIRE A LICENCE

Removal of asbestos by a person who does not hold a Class A or Class B asbestos removal licence is permitted if the asbestos being removed is:

Friable asbestos materials must not be removed by a person who does not have a Class A asbestos licence.

A worker carrying out asbestos removal work, including a self-employed person conducting a business or undertaking, must be trained in the identification and safe handling of asbestos prior to carrying out asbestos removal work without a licence. An asbestos awareness course or the nonfriable removal unit of competency would be considered appropriate training.

This allows a person (for example, a plumber) to remove small amounts of non-friable asbestos and replace it with non-asbestos alternatives if they come across it during renovations, refurbishments, or service and maintenance work. However, this person must still use safe working methods to ensure the work is not creating a risk to the health and safety of persons at the workplace.

The WHS Regulations require a person who is carrying out asbestos removal work without a licence to comply with the duties outlined in Chapter 4 of this Code and also with some of the duties in Chapter 3 of this Code. These duties are summarised below:

Although it is not mandatory for the person to prepare an asbestos removal control plan for this type of asbestos removal work, it may be beneficial to do so to ensure the work is being carried out safely. Refer to Section 3.5 for further information on an asbestos removal control plan.

It is also not mandatory to conduct air monitoring; however, an independent licensed asbestos assessor or competent person can carry out it out in these situations. Refer to Section 3.11 for further information on air monitoring.

Regulation 39: The WHS Regulations require that a person conducting a business or undertaking must ensure that information, training and instruction provided to a worker is suitable and adequate, having regard to:

The person must, so far as is reasonably practicable, ensure that the information, training and instruction is provided in a way that is readily understandable by any person to whom it is provided.

Regulation 445: The WHS Regulations require a person conducting a business or undertaking to ensure workers who they reasonably believe may be involved in asbestos removal work in the workplace or the carrying out of asbestos-related work are trained in the identification, safe handling and suitable control measures for asbestos and ACM.

This training may include the following topics:

This training is more general than the training that a worker undertaking licensed asbestos removal work would receive. Workers who are undertaking licensed asbestos removal work are required to complete specific units of competency. Refer to Section 3.2 for further information.

Records of all training must be kept while the worker is carrying out the work and for five years after the day the worker stops carrying out the work. These records must also be available for inspection by Comcare.


3. DUTIES FOR LICENSED ASBESTOS REMOVAL WORK

Licensed asbestos removal work can differ greatly depending on the type, quantity and condition of the asbestos or ACM being removed. There are a number of duties in the WHS Regulations to ensure licensed asbestos work is carried out safely and without releasing airborne asbestos and exposing workers and other persons.

A summary of the specific duties in the WHS Regulations are:

These requirements apply to a number of duty holders including the licensed asbestos removalist, the person who commissioned the asbestos removal work, and the person with management and control of the workplace. The duties are explained further below.


When licensed asbestos removal work is being carried out at a workplace, an asbestos removal supervisor must oversee the work. The licensed asbestos supervisor must have a certification appropriate to the type of licensed asbestos work.

If the asbestos removal work requires a Class A licence, for example removing friable asbestos, the asbestos removal supervisor must be present at the asbestos removal area whenever the work is being carried out.

However, if the asbestos removal work requires a Class B licence, for example non-friable asbestos that is more than 10 m², then the asbestos removal supervisor must be readily available to a worker who is carrying out the work whenever it is being carried out. For example, if the supervisor is contactable by phone and able to arrive at the workplace within 20 minutes, this would be regarded as accessible.

Where the asbestos removal work requires a Class B licence and it is being carried out by a self-employed person working alone, for example a plumber removing more than 10 m² of AC sheeting, the person must hold the competency of a worker for non-friable asbestos removal and the competency of a supervisor for non-friable asbestos removal.

A licensed asbestos removalist must not direct or allow a worker to carry out licensed asbestos removal work unless they are satisfied the worker holds a certification that is relevant to the class of licensed asbestos removal work they will be carrying out.

Workers (including the asbestos removal supervisors) who are carrying out licensed asbestos removal work are required to acquire a certification by completing units of competencies to show they have the relevant training to be able to remove asbestos. The units of competency completed by the person will determine what type of asbestos work they can carry out. Asbestos removal supervisors will have additional units of competency to complete.

Registered training organisations conduct training and education for the specific unit of competency for both Class A and Class B asbestos removal work as well as the asbestos removal supervisor certification. The Class B removal unit of competency must be completed before the Class A unit of competency. 

A licensed asbestos removalist must provide appropriate training to a worker carrying out licensed asbestos removal work at the workplace to ensure the work is carried out in accordance with the asbestos removal control plan for the workplace.

This is additional training to the general training that is provided on the identification and safe handling of asbestos and the appropriate controls referred to in the Code of Practice: How to Manage and Control Asbestos in the Workplace.

A worker who is carrying out licensed asbestos removal work must receive training that is designed specifically for the workplace where the work is being or is to be carried out. This should occur before the commencement of each asbestos removal job. The training should include:

If the worker is required to hold other licences for the particular task, for example a demolition licence, additional training may be provided to cover this type of work.

The licensed asbestos removalist must keep a record of all training undertaken by a worker who is carrying out licensed asbestos removal work:

The training record must be readily accessible at the asbestos removal area and available for inspection under the WHS Act.


Prior to any licensed asbestos removal work being carried out at a workplace, the licensed asbestos removalist must inform the person with management or control of the workplace about the work and the date it is to commence.

The person with management or control of the workplace must then ensure the following persons are told that the asbestos removal work is to be carried out and when the work is to commence:

If the workplace is a domestic premises, the licensed asbestos removalist must, so far as is reasonably practicable, before commencing the licensed asbestos removal work tell the following people about the asbestos removal work and when it will commence:

A licensed asbestos removalist must provide the following information to a person who is likely to be engaged to carry out the work:

Before commencing the licensed asbestos removal work, the licensed asbestos removalist must obtain a copy of the asbestos register for a workplace from the person with management or control of the workplace.

This provision does not apply if the work is being carried out at a domestic premise.

A licensed asbestos removalist must prepare an asbestos removal control plan for any licensed asbestos removal work they are commissioned to undertake.

An asbestos removal control plan is a document that identifies the specific control measures a licence holder will use to ensure workers and other persons are not at risk when asbestos removal work is being conducted. It is similar to a job safety analysis (JSA) but is focused on the specific control measures necessary to minimise any risk from exposure to asbestos.

An asbestos removal control plan helps ensure the asbestos removal is well planned and carried out in a safe manner. An asbestos removal control plan is only required to be prepared for licensed asbestos removal work. However, one can be prepared to assist when planning asbestos removal work that does not require a licence.

The licensed asbestos removalist must also take into account any asbestos register relevant to the asbestos to be removed and the area to be worked on. The structure of the asbestos removal control plan may be generic but each plan must address the specific situation/requirements for each job.

The asbestos removal control plan must be prepared before the licensed asbestos removal work commences.

The asbestos removal control plan must include details of:

 

Specifications or drawings that are relevant to the asbestos removal can also be attached to the asbestos removal control plan to provide additional information about the asbestos.

Appendix A provides further detail of what can be in a comprehensive asbestos removal control plan.

When preparing the asbestos removal control plan, the licensed asbestos removalist should consult with the person who commissioned the work, the person with management or control of the workplace (if not the same person), workers and their health and safety representatives.

For the same reasons, if licensed asbestos removal  work is being carried out at domestic premises, the licensed asbestos removalist should consult with the person who commissioned the removal work, the owner or the occupier (if not the same person).

Once the asbestos removal control plan is prepared, a copy must be:

The asbestos removal control plan must also be made available for inspection under the WHS Act.


A licensed asbestos removalist must notify Comcare in writing at least five days before the licensed asbestos removal work commences. 

The following information must be included in the notification:

It may not be possible to provide five days notice, and removal work may commence immediately in the following limited circumstances:

If this is the case, the licensed asbestos removalist must notify Comcare immediately by telephone and in writing within 24 hours after the notice provided over the telephone. 

A person who is carrying out licensed asbestos removal work must ensure that signs indicate where the asbestos removal work is being carried out and barricades are erected to delineate the asbestos area. This will assist in limiting access to the asbestos removal work area.

If the person who commissions the licensed asbestos removal work and the person with management or control of the workplace (if not the same person) is aware that licensed asbestos removal work is being carried out, they must ensure that access to the removal area is limited to the following people:

A combination of using signs and barricades may be necessary to limit access to the asbestos removal area, for example installing a fence and signs may be used as a method to inform people that it is the asbestos removal area. Using locking access doors may be appropriate as long it does not create an evacuation hazard.

All people who have access to the removal area should comply with any direction given by the licensed asbestos removalist.

Section 4.2 of this Code provides further detail on the type of signs and barricades that should be used at a workplace.


When carrying out licensed asbestos removal work, the licensed asbestos removalist must ensure decontamination facilities are available for the asbestos removal work area, any plant used in that area and workers carrying out the asbestos removal work.  

Section 4.6 of this Code outlines decontamination procedures that can be put in place at the workplace.

When carrying out licensed asbestos removal work, the licensed asbestos removalist must ensure that asbestos waste is contained and labelled in accordance with the GHS before the waste is removed from the asbestos removal area. It must be disposed of as soon as is practicable at a site authorised to accept asbestos waste. 

Disposable PPE that has been used in the asbestos work area and is contaminated with asbestos must be sealed and labelled in a container and disposed of upon completion of the asbestos removal work.

In some cases, it may not be reasonably practicable to dispose of PPE that is clothing. In this case, the clothing must be laundered at a laundry that is equipped to launder asbestos-contaminated clothing. If this cannot be done, the clothing must be sealed in a container until is reused for asbestos removal purposes.

It may also not be reasonably practicable to dispose of PPE that is not clothing. If this is the case, the PPE must be decontaminated prior to it being removed from the asbestos removal area. If this cannot be done, the PPE must be sealed in a container until it is reused for asbestos removal purposes.

Where a sealed container has been used, it must be decontaminated and labelled in accordance with the GHS prior to it being removed from the asbestos removal area to indicate that it contains asbestos.

Section 4.5 of this Code provides guidance on the type of PPE that can be used. Section 4.8 of this Code outlines waste containment and disposal procedures that can be implemented at the workplace.


A person commissioning licensed asbestos removal work must ensure that, once the licensed asbestos removal work has been completed, a clearance inspection is carried out and a clearance certificate is issued before the workplace can be re-occupied by:

This also includes where the work is being carried out at domestic premises.

To be independent, the licensed asbestos assessor or competent person must not be involved in the removal of asbestos for that specific job and is not involved in a business or undertaking involved in the removal of the asbestos for that specific job.

In some cases, it may not be reasonably practicable for the licensed asbestos assessor or competent person to be independent from the person who carried out the asbestos removal work. If this is the case, the person commissioning the work can apply to Comcare for an exemption from this requirement under Part 11.2 of the WHS Regulations.

The independent licensed assessor or competent person must not issue a clearance certificate unless they are satisfied that the asbestos removal area and the area immediately surrounding it are free from visible asbestos contamination. To do this, they can conduct a visual inspection for evidence of dust and debris. If air monitoring was also conducted, the results of that test must show that asbestos is below 0.01 fibres/ml.

If a clearance certificate has not been obtained, the asbestos removal area must not be reoccupied for normal use or other work activities. A clearance certificate must be issued before the area can be re-occupied for demolition or other work.

Unauthorised persons cannot enter the asbestos removal work area prior to a clearance certificate being issued and any protective barricades should remain in place until completion of all licensed asbestos removal work and the final clearance certificate is issued.

Appendix C provides an example of a clearance certificate.

Air monitoring involves sampling airborne asbestos fibres to assist in assessing exposure to asbestos and the effectiveness of implemented control measures. It must be conducted in accordance with the Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Dust, 2nd Edition [NOHSC: 3003 (2005)].

Air monitoring requirements will vary depending on the type of asbestos being removed, the location and position of the asbestos, if an enclosure is used and whether the asbestos removal work is within a building or outside.

Air monitoring may be required when:

The air monitoring must be conducted before and during Class A asbestos removal work. However, it is not required before friable asbestos removal work commences when the glove bag removal technique is used. Air monitoring must be carried out as part of the clearance inspection, for instance at the conclusion of the asbestos removal work.

A person who commissions asbestos removal work that requires a Class A licence must ensure that an independent licensed asbestos assessor undertakes air monitoring of the asbestos removal area at the workplace.

In relation to removal work requiring a licence:

Where air monitoring is otherwise required, for instance to determine whether the exposure standard has been exceeded following an uncontrolled disturbance or release of asbestos at the workplace, an independent licensed asbestos assessor or competent person may carry it out. However, if the release involves friable asbestos, only an independent licensed asbestos assessor can carry out the air monitoring.

Once the results of the air monitoring are received, the licensed asbestos removalist must take action depending on the respirable asbestos fibre level. Where the results show that respirable asbestos fibre levels exceed the action levels outlined in Table 1, action must be taken immediately.


Action level

Control

Action

Less than 0.01 fibres/ml

No new control measures are necessary

Continue with control measures

At 0.01 fibres/ml or more than 0.01 fibres/ml but less than or equal to 0.02 fibres/ml

1. Review

 

Review control measures

2. Investigate

 

Investigate the cause

3. Implement

Implement controls to eliminate or minimise exposure and prevent further release

More than 0.02 fibres/ml

1. Stop removal work

Stop removal work

2. Notify Comcare

Notify Comcare by phone followed by fax or written statement that work has ceased and the results of the air monitoring

3. Investigate the cause

Conduct a thorough visual inspection of the enclosure (if used) and associated equipment in consultation with all workers involved with the removal work

4. Implement controls to eliminate or minimise exposure and prevent further release

Extend the isolated/barricaded area around the removal area/enclosure as far as reasonably practicable (until fibre levels are at or below 0.01 fibres/ml, wet wipe and vacuum the surrounding area, seal any identified leaks (e.g. with expandable foam or tape) and smoke test the enclosure until it is satisfactorily sealed.

5. Do not recommence removal work until further air monitoring is conducted

Do not recommence until fibre levels are at or below 0.01 fibres/ml

Table 1: Air monitoring action levels.

Any information that is gathered from these actions can be referred to during future asbestos removal jobs (where applicable).

The person who commissions the licensed asbestos removal work must ensure the results of the air monitoring are given to the following persons:

If the workplace is domestic premises, the licensed asbestos removalist must ensure the results are given to the following persons:

When a licensed asbestos removalist is removing friable asbestos (requiring a Class A licence), the following must occur, so far as is reasonably practicable:

However, if glove bags are used, negative pressure and conducting air monitoring prior to the work commencing are not required.

The enclosure must not be dismantled until the results are received from:

The results must show that the respirable asbestos fibre level is below 0.01 fibres/ml.

The enclosure must be decontaminated prior to dismantling it to minimise, so far as is reasonably practicable, the release of respirable asbestos fibres. The person who commissions the removal of the friable asbestos must obtain a clearance certificate from the licensed asbestos assessor after the enclosure has been dismantled.

Chapter 6 provides further detail on enclosures. Section 4.3 provides further detail on the wet method. Section 7.2 provides further detail on glove bags.


4. CONTROLS APPLICABLE TO ALL TYPES OF ASBESTOS REMOVAL

This chapter applies to all asbestos removal work i.e. Class A and Class B licensed asbestos removal work and asbestos removal work that does not require a licence.

An asbestos removalist should consider not only the direct hazards that are associated with the asbestos removal work but also those hazards related to the work activity and the work environment (for example, demolition or construction).

Removing asbestos in a confined space should only be undertaken where it is not possible to avoid doing work in that space. A safe system of work should be developed for inclusion in the management plan or removal control plan.

Friable asbestos removal requires the use of enclosures that are designed to eliminate or minimise the release of airborne asbestos spreading from the asbestos removal work area.

Depending on the conditions inside the enclosure, an asbestos enclosure may also become a confined space.

Further information is available in the Code of Practice: Confined Spaces.

Work at heights should not be undertaken if the task can be performed on the ground. If asbestos removal work must be undertaken at height, then the relevant WHS Regulations apply.

Further information is available in the Code of Practice: How to Prevent Falls at Workplaces.

Heat-related hazards can be created from working in enclosures or confined spaces or using PPE. The factors that can lead to heat stress should be considered, including temperature, humidity, air movement, exposure to a heat source, work activities and demands, how long the PPE must be worn and individual physical factors.

Control measures include:

Further information is available in the Code of Practice: Managing the Work Environment and Facilities.

When undertaking asbestos removal work, the risk associated with electrical equipment should be controlled by following the procedures set out below.   

All portable electrical tools and equipment, including flexible leads and any electrical installations utilised by workers during asbestos removal, should comply with AS/NZS 3012:2003 Electrical installations – construction and demolition sites.

Further information is available in the Code of Practice: Managing Risks with Electrical Work.


The asbestos removalist must use signs and barricades to clearly indicate the area where the asbestos removal work is being performed. Signs must be placed in positions so that people are aware of where the asbestos removal work area is and should remain in place until removal is completed and clearance to reoccupy has been granted. Responsibilities for the security and safety of the asbestos removal site and removal work area should be specified in the asbestos removal control plan (where required). This includes inaccessible areas that are likely to contain asbestos.

Warning signs must be placed so they inform all people nearby that asbestos removal work is taking place in the area. Signs should be placed at all of the main entry points to the asbestos removal work area where asbestos is present.

These signs should be weatherproof, constructed of light-weight material and adequately secured so they remain in prominent locations. The signs should be in accordance with AS 1319-1994 Safety signs for the occupational environment for size, illumination, location and maintenance.

The use of barricades assists with traffic control and prevents access to the removal site and removal work area.

The purpose of barricades is to delineate and isolate the asbestos removal area with appropriately placed barricades. Barricades can take various forms, from tape to solid hoarding. The type of barricading should reflect the level of risk. For friable asbestos removal work, solid barricades should be used. Tape may be appropriate for non-friable asbestos removal work of short duration.

The location of barricades will depend on the physical environment and the level of risk. An assessment of the asbestos removal work site should determine the appropriate placement of barricades.

For example, a non-friable asbestos cement removal job where the asbestos cement is in good condition may use a wall located three metres from the asbestos removal area as the barrier. A friable sprayed asbestos removal job being performed dry due to electrical restrictions may require a barricade 15 metres from the asbestos removal area.

In determining the distance between barriers and the asbestos removal area, the following should be considered:

An asbestos removalist must use techniques to eliminate or minimise the generation of asbestos fibres so far as is reasonably practicable. They must choose the method of asbestos removal that is most effective at minimising fibre release at the source. The removal methods are listed in preferred order:

The wet spray method is the preferred asbestos removal method and should be used for the removal of asbestos from structures and plant. The wet spray method requires the use of a constant low-pressure water supply for wetting down asbestos and related items to suppress asbestos fibres. This can be achieved with a mains-supplied garden hose fitted with a pistol grip. If no water supply is readily available, a portable pressurised vessel (for example, a pump-up garden sprayer) may be used.

 

The design of the spraying equipment will depend on the availability of a water supply and access to the area to be sprayed.

The wet spray method involves applying a fine water spray to the asbestos in a manner that ensures the entire surface of the asbestos is saturated and the run-off is minimised. The asbestos should be maintained in a wet condition throughout the removal.

A wetting agent (surfactant), for example detergent, may be added to the water to facilitate more rapid wetting of the asbestos. A manually controlled, consistent low-pressure, fine spray (for example, from an adjustable pistol-grip garden hose) is recommended.  

For very small areas, a small spray water bottle may be sufficient. In all cases, the use of water should be in the form of a mist to minimise the potential to generate respirable dust.

The asbestos should be wetted through to its full depth and the water spray should be directed at the site of the cut. The wetted material should be removed as the cut is progressed.

Immediately after the asbestos is removed from its fixed or installed position, spray should be directed on sides previously not exposed.

The wet friable asbestos removed in sections should immediately be placed in suitably labelled asbestos waste containers and properly sealed along with any small sections dislodged as the asbestos is cut.

Wherever reasonably practicable, a HEPA-fitted vacuum cleaner should be used in conjunction with the wet spray method. The HEPA vacuum cleaner should be used prior to spraying asbestos with water and for the collection of any dust spread over a large area.

Airborne asbestos fibres are significantly suppressed when the wet spray method is used; however, they are not entirely eliminated so effective PPE including RPE is also essential. Refer to Section 4.5 of this Code for information on RPE.

Consideration should be given to applying a PVA emulsion as it may be more effective than water (with a wetting agent) in minimising fibre release. For example, PVA can be applied and allowed to dry on asbestos cement roofing prior to its removal as an alternative method to prevent slip hazards.

The soaking method with total saturation should be used if the asbestos is so thick that the spray method will not suppress the asbestos significantly. This method involves injecting water or a water-based solution directly into friable asbestos. It is a process that requires specific training in relation to the use of the equipment and the process.

The asbestos is soaked by the introduction of water or other wetting agents through an appropriate applicator that consists of an injection head with numerous side holes or outlets through which the water or wetting agent is fed to the asbestos.

To facilitate more rapid wetting of the asbestos, holes or cuts should be made in the outer covering to enable the water or wetting agent to be injected in such a manner as to ensure that the asbestos is saturated but not just washed out through a liquid passage.

The soaking should be done before removal. The quantity of water or wetting agent and the time to soak will depend on the thickness of the asbestos, access to the asbestos and location of the holes.

The saturated asbestos should then be removed in sections, placed in a properly labelled container, sealed and disposed of as with the spray method.

The dry method is not preferred as there is a much greater potential for airborne asbestos fibres to be generated. The dry removal method can only be used if the wet spray or soaking methods are not suitable, for example if there are live electrical conductors or if major electrical equipment could be permanently damaged or made dangerous by contact with water.

If the dry removal method is used, the following controls should be implemented:

Tools and equipment that can be used during asbestos removal work include asbestos vacuum cleaners, manually operated hand tools and equipmentother than compressed air or high pressure water spraythat have been designed to capture or suppress respirable dust or are used in a way that is designed to capture or suppress respirable dust.

In addition to any equipment required to complete a particular task, the following equipment may be required on-site before the work begins:

Tools and equipment that generate dust must not be used on asbestos. These include:

The use of tools and equipment that cause the release of asbestos, including power tools and brooms, may be used on asbestos if the equipment is enclosed and/or designed to capture or suppress asbestos fibres and/or the equipment is used in a way that is designed to capture or suppress asbestos fibres safely, for example:

Controls are assumed to be effective if exposure monitoring results are less than 0.05 f/ml or control monitoring results are less than 0.01 f/ml. Should either of these values be exceeded during monitoring, work must cease and the control measures that are in place reviewed or improved to ensure the levels of airborne asbestos do not exceed these levels.

After the asbestos removal work is completed, tools must be decontaminated (refer to Section 4.6).

All equipment used for the removal of asbestos should be inspected before the commencement of the asbestos removal work, after any repairs and at least once every seven days when it is continually being used. A register with the details of these inspections, the state of the equipment and any repair details should be maintained.

Asbestos vacuum cleaners should comply with the Class H requirements in Australian Standard AS/NZS 60335.2.69 Industrial vacuum cleaners or its equivalent. Asbestos vacuum cleaners should not be used on wet materials or surfaces. Attachments with brushes should not be used as they are difficult to decontaminate.

Filters for these vacuum cleaners should conform to the requirements of AS 4260-1997 High efficiency particulate air (HEPA) filters – Classification, construction and performance or its equivalent.

Household vacuum cleaners must never be used where asbestos is or may be present, even if they have a HEPA filter.

Asbestos vacuum cleaners can only be used for collecting small pieces of asbestos dust and debris. Larger pieces should be picked up and placed in suitable waste containers and should never be broken into smaller sizes for vacuuming.

The asbestos removalist should ensure that procedures are established for the general maintenance, including emptying, of asbestos vacuum cleaners in a controlled environment.

They should be cleaned externally with a wet cloth after each task, the hose and attachments should be stored in a labelled impervious bag, and a cap should be placed over the opening to the asbestos vacuum cleaner when the attachments are removed.

PPE should be worn whenever an asbestos vacuum cleaner is opened to change the bag or filter or to perform other maintenance.

The emptying of asbestos vacuum cleaners can be hazardous if the correct procedures are not followed. Asbestos vacuum cleaners should only be emptied by a competent person with the correct PPE, in a controlled environment and in compliance with the manufacturer’s instructions.

Whenever possible, asbestos vacuum cleaners should not be hired, as they can be difficult to fully decontaminate.

Hiring may be more viable in some instances if they are completely decontaminated, such as when a one-off maintenance task is required for asbestos. Asbestos vacuum cleaners should be hired only from organisations that provide vacuum cleaners specifically for work involving asbestos and the asbestos vacuum cleaner has been previously decontaminated. If hired, the asbestos vacuum cleaner should be decontaminated before it is returned.

Alternatively, the hire organisation may undertake the decontamination and maintenance of the filters and bags of the asbestos vacuum cleaner itself. In these cases, the asbestos vacuum cleaner should be hired out in a sealed storage container, with instructions that it may be removed from the container only when it is inside the asbestos removal work area and users are wearing appropriate PPE. When the minor maintenance work is completed the asbestos vacuum cleaner should be resealed in the storage container provided, and the sealed storage container should then be decontaminated by wet wiping before it is removed from the removal work area and returned to the hire organisation for decontamination and maintenance.

Organisations that hire out asbestos vacuum cleaners should ensure all their asbestos vacuum cleaners are decontaminated, maintained in good working order and the hirers are competent in their safe use. It is suggested that asbestos vacuum cleaners are only hired out to asbestos removal supervisors or licence holders.

At the completion of the asbestos removal work, the tools and equipment must be decontaminated, placed in sealed, labelled containers and if necessary, disposed of as asbestos waste. The asbestos vacuum cleaner and attachments must also be decontaminated. The bag and filter must be removed in accordance with the manufacturer’s instructions and disposed of as asbestos waste.

Spray equipment includes wet sprays with water mist or wetting solution. A constant low-pressure water supply is required for wetting down asbestos and related items to suppress airborne asbestos fibres.

Wet spray can be achieved with a mains-supplied garden hose fitted with a pistol grip. If no water supply is readily available, a portable pressurised vessel (such as a pump-up garden sprayer) may be used. For very small areas, a small spray water bottle may be sufficient. In all cases, the use of water should be in the form of a mist to minimise the potential to generate airborne dust.

An asbestos removalist must provide all workers with PPE that is suitable for asbestos removal work. Workers must also use the PPE given to them by the asbestos removalists. PPE must be worn at all times during the work in the removal area. PPE includes clothing, for example coveralls, gloves and safety footwear, as well as RPE. The appropriate PPE can be determined by conducting a risk assessment.

Personal protective clothing should be made from materials that provide protection against fibre penetration and not from wool or other materials that attract fibrous dusts.

All equipment used for the removal of asbestos should be inspected before the commencement of the asbestos removal work, after any repairs and at least once every seven days when it is continually being used. A register with the details of these inspections, the state of the equipment and any repair details should be maintained.

At the end of the asbestos removal work and upon leaving the asbestos removal work area, all PPE must be disposed of as asbestos waste or decontaminated and stored in sealed double bags before being removed from the asbestos removal site to be laundered by a laundry with facilities for laundering asbestos-contaminated materials. PPE should be thoroughly wet before being placed in bags.

Disposable coveralls should be provided wherever reasonably practicable and should be:

Coveralls should:

If it is not reasonably practicable to provide coveralls that can be disposed of after a single use, the coveralls may be laundered at a commercial laundry equipped to launder asbestos-contaminated clothing by prior arrangement. The coveralls must be sealed in a decontaminated container before they are removed from the asbestos removal work area. However, laundering of asbestos-contaminated protective clothing is not recommended because decontamination cannot be guaranteed. It is recommended that such re-usable coveralls should only be used in limited instances, for example in emergency services where the coveralls must be inflammable to protect against fire hazards and continual disposal and replacement is not practicable. Refer to Section 4.8 for more information on laundering of contaminated clothing.

In some cases (particularly dusty jobs) double coveralls should be used, with the outer coverall being removed a predetermined distance from the final decontamination area. Disposable coveralls should be wrapped in a double layer of plastic before disposal as asbestos-contaminated waste after the removal task is completed.

If significant quantities of asbestos fibres may be present, single-use disposable gloves should be worn. If latex gloves must be used, low protein (powder free) gloves should be used. If latex gloves are not available, disposable nitrile gloves can be used as an alternative.

Gloves used for asbestos removal work should be disposed of as asbestos waste and the workers should clean their hands and fingernails thoroughly whenever leaving the asbestos removal work area. However, as with coveralls, if it is not reasonably practicable to use disposable gloves, they may be laundered appropriately in limited circumstances.

Safety footwear (for example, steel-capped, rubber-soled work shoes or gumboots) should be provided for all workers removing asbestos. Footwear should be laceless, as laces and eyelets can be contaminated and are difficult to clean. It should remain inside the barricaded area or dirty decontamination area for the duration of the asbestos removal work and should not be shared for hygiene reasons. Disposable overshoes should be avoided unless they are of a design that has an anti-slip sole.

When safety footwear is not in use, it should be stored upside down to minimise asbestos contamination inside the footwear. Storage facilities should be provided to allow for storage of the shoes. At the end of the removal work and each time the worker leaves the asbestos removal work area, safety footwear must be:

All workers engaged in removal work must wear RPE conforming to the requirements of AS/NZS 1716:2009 Selection, Use and Maintenance of Respiratory Protective Devices or its equivalent.

The level of respiratory protection and supplied air respirators should be determined by a competent person. The selection of suitable RPE depends on the nature of the removal work, the probable maximum concentrations of asbestos fibres expected and any personal characteristics of the wearer that may affect the facial fit of the respirator (for example, facial hair and glasses).

Disposable RPE is not preferred, however if selected, it should be stored in a suitable and clean location before use and disposed of after a single use.

A competent person may change the level of RPE at any stage during the removal process following an assessment of the asbestos fibre levels experienced inside the removal work area. For example, this may occur during the final clean-up after the removal of friable asbestos when the use of air-lines is no longer considered necessary.

If a medical condition precludes the use of negative pressure respirators, workers should be provided with a continuous-flow, positive pressure respirator wherever possible.

At every asbestos removal job, the workers should be reinstructed in the necessity to wear RPE correctly to guard against complacency.

A fit test should be performed to ensure the RPE fits the individual and provides a good face seal between the worker’s skin and the face piece. Fit tests should be repeated when changing from different models of RPE or a different sized face piece. 

Appendix B provides more information on selecting suitable RPE and fit tests.

Using and maintaining RPE

RPE must be worn at all times in the asbestos removal area and until the appropriate stage of personal decontamination.

Asbestos removalists or asbestos removal supervisors must ensure all workers undertaking any asbestos removal work receive instruction and training in:

The respirator must be worn in accordance with the manufacturer’s instructions and the coverall hood must go over the respirator straps. It should be examined in accordance with the manufacturer’s instructions before use to ensure that it is not damaged and is in good working order. Respirator defects should be reported immediately to the asbestos removal supervisor. The pre-use examination should include an inspection of:

Non-disposable respirators should be cleaned, disinfected and stored in a safe place away from the asbestos-contaminated removal area.

The length of time a particulate filter can be used for the asbestos removal work depends on the resistance to breathing and damage to the filter. The filter should be replaced if damaged or when resistance increases. A damaged filter must be replaced before resistance begins to increase. The replacement should be according to the manufacturer’s instructions.

Certain brands of filters may not be usable after being exposed to certain conditions such as a full decontamination shower. Specific advice should be sought from the supplier regarding the effectiveness of a filter after being subjected to certain conditions.

All parts, including filters, valves and seals, should be inspected before and after each use. Respirator defects should be reported immediately to the supervisor for repair or replacement.

A system of regular cleaning, inspection and maintenance of non-disposable respirators should be in place to ensure they are clean and in a safe working condition.

Records of all respirator issues, uses and maintenance should be kept up-to-date.

At the end of a shift or at a break, as part of the decontamination process, ensure the respirator is taken off last.

Air-line respirators are used when the asbestos being removed is friable. When in use, the air-line should incorporate a belt-mounted back-up filter. If a failure of the air supply system occurs, workers should leave the asbestos removal work area using normal decontamination procedures; the use of a back-up belt-mounted filter device allows for adequate respiratory protection during this process.

If the number of workers wearing air-line respirators inside an enclosure is likely to result in the tangling of air lines, manifolds should be provided to minimise this tangling and assist workers in moving around the enclosure.

The capacity of the compressor should be adequate for the number of air-lines, and the location of the compressor’s air intake should be assessed to ensure appropriate air quality and avoid contamination. Air from a compressor must be filtered before supply to a respirator.

Decontamination for the work area, workers, PPE and tools used in asbestos removal work is an important process in eliminating or minimising exposure to airborne asbestos fibres, particularly to persons outside the asbestos removal work area.

To determine the appropriate decontamination procedure, the risks of each individual asbestos removal job should be assessed.

There are two types of decontamination processes:

Contaminated items, tools, equipment and clothing must not be removed from the removal work area unless they have been decontaminated or contained.

If an item is not able to be decontaminated, or is not suitable for decontamination, it should be placed in a sealed container and disposed of in accordance with the WHS Regulations. The sealed container must be decontaminated before it is removed from the asbestos removal work area.

If removal work involves friable asbestos, the decontamination procedures must include decontamination units. Glove bag and wrap and cut methods are exceptions where personal decontamination procedures are likely to be satisfactory and units are not necessary. Mini-enclosure removals may require a combination of personal decontamination and decontamination units.

All tools used during asbestos removal work should be fully dismantled (where appropriate), cleaned under controlled conditions and decontaminated using either the wet or dry decontamination procedures described above before they are removed from the removal work area. The method chosen will depend on its practicality, the level of contamination and the presence of any electrical hazards.

If tools cannot be decontaminated in the asbestos removal work area, or are to be reused at another asbestos removal work area, they should be:

The bags containing the tools must remain sealed until decontamination or the commencement of the next asbestos maintenance or service task where the equipment can be taken into the removal work area and reused under full control conditions.

PPE should be worn when opening the bag to clean or reuse the equipment or tools, and decontamination should only be performed in a controlled environment.

In some circumstances it may be better to dispose of contaminated tools and equipment, depending on the level of contamination and the ease of replacement.

Personal decontamination involves the removal of all visible asbestos dust/residue from PPE and RPE. Personal decontamination must be undertaken each time a worker leaves the asbestos removal work area and at the completion of the asbestos maintenance or service work. Personal decontamination should be done within the asbestos removal work area to avoid recontamination. Personal decontamination should be carried out where a decontamination unit is not necessary such as during minor or small scale removal and maintenance work.

Asbestos-contaminated PPE must not be transported outside the asbestos removal work area except for disposal purposes. Before work clothes and footwear worn during asbestos removal work are removed from the asbestos removal work area for any reason, they should be thoroughly vacuumed with an asbestos vacuum cleaner to remove any asbestos fibres and the footwear should also be wet wiped.

RPE should be used until all contaminated disposable coveralls and clothing has been vacuum cleaned and/or removed and bagged for disposal and personal washing has been completed. Any PPE used while carrying out asbestos removal work must not be taken home by a worker.

Personal hygiene and careful washing are essential. Particular attention should be paid to the hands, fingernails, face and head.


PERSONAL DECONTAMINATION

Never leave the asbestos removal work area until decontamination is complete.

The asbestos removalist must ensure particular areas are set up for people to personally decontaminate themselves and any tools and equipment when they are entering and leaving the asbestos removal work area to eliminate or minimise airborne asbestos from being released from the asbestos removal work area.

These areas are:

Below is an example of how a person would enter and leave a removal work area.

Figure 1: Decontamination unit.

A risk assessment should be conducted to determine the number of units required based on the number of workers in the asbestos removal work area. As a guide, one decontamination unit should be provided for every six workers in the asbestos removal work area. 

Where men and women are required to use the same decontamination unit, a system of work needs to be implemented to enable them to access the unit separately. In many instances, the only satisfactory way of providing appropriate changing facilities is to provide a mobile or specially constructed on-site decontamination unit.

The decontamination unit should be immediately adjacent to and directly connected with the enclosed removal work area. It should be located as far away as practicable from amenities and lunch rooms.

The decontamination unit should include a dirty decontamination area, a clean decontamination area and a clean changing area. These areas need to:

Towels and soap should be provided to allow workers to appropriately decontaminate themselves.

All water from the decontamination facility should pass through a particulate filter or other trap before it passes into sewer mains. The filter or trap should be capable of capturing particles down to 5 µm.

Workers should not smoke, eat or drink in any part of the decontamination unit.

The asbestos removalist may want to have a worker stationed outside an enclosure for the duration of the removal work to liaise with the project supervisor, communicate with personnel inside the work enclosure and instigate emergency/evacuation procedures if necessary.

Records about these activities should be kept on a daily basis.

Remote decontamination units are decontamination units not attached to an enclosure when friable asbestos is being removed. Remote units are not located next to the asbestos removal work area and can only be used if a decontamination unit cannot be located immediately adjacent to the asbestos removal work area.

When a remote decontamination unit is to be used, the asbestos removalist would need to implement additional transiting procedures to minimise asbestos contamination of pathways leading from the enclosure to the decontamination unit. These procedures are longer and more complex than non-transiting. This involves the use of ‘transiting’ PPE and additional facilities to enable the worker to carry out preliminary decontamination before travelling to the decontamination unit for full decontamination.

This may include a three-stage airlock isolated changing area, which should be specially constructed and made of 200 µm thick polythene sheeting. The area should be attached to the enclosure and should comprise three compartments separated by weighted sheets to minimise the spread of dust between the compartments.

Before workers enter this changing area, all obvious signs of asbestos dust need to be removed from their protective clothing using an asbestos vacuum cleaner. The isolated changing area is then used to discard outer garments, including coveralls and overshoes, before workers can put on fresh outer/protective clothing for the journey to the decontamination unit. RPE should be worn until the appropriate phase of the decontamination procedure within the remote decontamination unit.

The route of access from the asbestos removal area to the decontamination unit should be suitably signposted and barricaded to restrict public access.

Air monitoring must be conducted in the immediate vicinity of this access route and at other suitable locations outside the asbestos removal area.

Figure 2: Decontamination area.


Disposable coveralls should be used as protective clothing unless it is not reasonably practicable to do so. When non-disposable protective clothing is used, the contaminated clothing must be laundered in a suitable laundering facility that is equipped to launder asbestos-contaminated clothing. Contaminated protective clothing must not be laundered in homes. Any clothing worn under coveralls must be disposed of or suitably bagged for laundering as asbestos-contaminated clothing.

The laundering facility that is equipped to launder asbestos-contaminated clothing:

The contaminated clothing should:

At the laundry facility:

An asbestos removalist should design the route for removal of the asbestos waste bags or containers through the asbestos removal work area prior to commencement of the asbestos removal work. Only unused bags and heavy-duty 200 µm (minimum thickness) polythene sheeting can be used. Bags labelled for asbestos waste should not be used for any other purpose.

When developing a waste disposal program, the following should be taken into account:

The development of the waste disposal program and methods used to transport waste through a building needs to be determined by a competent person (usually the asbestos removal supervisor) following discussions with the person with management or control. In occupied workplaces, all movement of waste containers through a building should take place outside normal working hours.

The waste disposal program should be included in the asbestos removal control plan and specify the method of transport and routes to be used for removing waste from the asbestos removal area before the commencement of each removal.

Loose asbestos waste must not accumulate within the asbestos removal work area by containing the waste in labelled asbestos waste bags or wrapped in plastic. Once the asbestos waste has been removed from the asbestos removal area, it should either be placed in a solid waste drum, bin or skip for secure storage and eventual disposal, or removed immediately from the site by an environmental protection agency (EPA) approved/licensed carrier for disposal.

The asbestos waste must be disposed of at a licensed asbestos waste disposal site. The disposal process must be in a manner that eliminates the release of airborne asbestos fibres by ensuring:

The asbestos waste must be disposed of as soon as reasonably practicable, whether that is:

All asbestos waste, friable asbestos and small pieces of non-friable asbestos must be contained to prevent exposure to airborne asbestos fibres. Containment is to be in new heavy-duty 200 µm (minimum thickness) polythene bags that are no more than 1200 mm long and 900mm wide to prevent manual task injuries.  

Controlled wetting of the asbestos waste should be carried out to minimise asbestos dust emissions during bag/polythene sealing or any subsequent rupture of the bag or wrapped bundles. The bags must be twisted tightly and have the neck folded over and secured with adhesive tape (referred to as goose-necking).

To minimise the risk of a bag tearing or splitting and to assist in manual handling, asbestos waste bags should not be filled more than half full (depending on the weight of the items) and excess air should be gently evacuated from the waste bag in a way that does not cause the release of dust.

The bags should be labelled with appropriate signage stating that they contain asbestos and that dust creation and inhalation should be avoided.

The external surface of each bag should be cleaned to remove any adhering dust before the bag is removed from the asbestos removal work area and double bagged outside the asbestos removal areas immediately following the decontamination process.

Asbestos sheeting and redundant asbestos-lagged pipes and equipment should be contained in heavy-duty 200 µm (minimum thickness) polythene sheeting.

Polythene sheeting should be new (not recycled) as recycled sheeting can have flaws in it. Once wrapped in plastic, the bundles need to be labelled to indicate they contain asbestos so they can be treated appropriately.

Asbestos sheeting and redundant asbestos-lagged pipes and equipment should be double wrapped in the polythene sheeting and adhesive tape applied to the entire length of every overlap to secure the bundles to minimise the risk of the polythene sheeting tearing or splitting.

Once the waste has been removed from the asbestos removal work area, it should either be:

All containers containing a hazardous chemical such as asbestos must conform to the labelling elements of the GHS. The waste drums or bins should be lined with plastic (minimum 200 μm thickness), and labels warning of the asbestos waste should be placed on the top and side of each drum or bin with the words, ‘Danger: Asbestos Do not break seal’ or a similar warning.

Examples of labels are included below.

Label 1: Sample asbestos waste bag.

Sign 1: Sample asbestos removal area.

All drums or bins used for the storage and disposal of asbestos waste should be in good condition with lids and rims in good working order and free of hazardous residue.

The drums or bins should:

Controlled wetting of the waste during drum or bin filling should be carried out to minimise asbestos dust emissions. 

Drums or bins used to store asbestos waste must be stored in a secure location when they are not in use. They should not be moved manually once they have been filled. Trolleys or drum lifters should be used.

If the drum or bin is to be reused, the asbestos waste should be packed and sealed so that when the drum or bin is emptied there is no residual asbestos contamination. The drum or bin should be inspected after use to ensure there is no asbestos residue.

If the volume or size of the asbestos waste cannot be contained in asbestos waste bags, drums or bins, a waste skip, vehicle tray or similar container in good condition should be used.

The asbestos should be sealed in double-lined, heavy-duty plastic sheeting or double bagged before it is placed in the skip. However, non-friable asbestos waste may be placed directly into a skip or vehicle tray that has been double-lined with heavy-duty plastic sheeting (200 µm minimum thickness) provided it is kept damp to minimise the generation of airborne asbestos.

Once the skip is full, its contents should be completely sealed with the plastic sheeting. If the skip is emptied at a waste disposal site, procedures for containment of the plastic lining to prevent tearing should be developed.

If asbestos waste cannot be disposed of immediately, the skip may be used for storing the asbestos waste on site over a period of time provided that the contents are secured (for example, using a lockable lid or locating the skip in a secure area) to prevent unauthorised access. 

Disposal of asbestos waste is the final step in the process of asbestos removal work. It is therefore the last point at which the exposure to risks associated with asbestos is likely to occur. The asbestos waste must be disposed of as soon as is practicable at a licensed asbestos disposal site.

The transport of commercial asbestos waste is covered under EPA legislation. Disposal sites are regulated by the EPA and local government regulations.


5. USING AN ENCLOSURE DURING LARGE SCALE REMOVAL WORK

Large scale asbestos removal includes removal that occurs on a frequent basis, is generally of a longer duration, usually generates a significant amount of airborne asbestos fibres and may pose a serious risk both to workers and others. 

Where friable asbestos is removed, a licensed asbestos removalist that holds a Class A licence must remove the asbestos. The licensed asbestos removalist must ensure, so far as is reasonably practicable, the asbestos removal work area is enclosed (sometimes referred to as the ‘bubble’) to eliminate or minimise the release of airborne asbestos fibres.  

When large scale friable asbestos removal work is being undertaken, the asbestos removal work areas should be enclosed and under ‘negative pressure’ with the use of negative air pressure units.

The use of enclosures in large scale non-friable asbestos removal requiring a Class B licence should be determined on the basis of a risk assessment. Factors such as proximity to other work areas, weather conditions if outdoors, and the amount of material to be removed should be considered.

The design and installation of the enclosure should consider:

The enclosure should:

During the masking up and later removal of the sheeting, all persons must wear appropriate PPE, for example coveralls, and as a minimum a half-face respirator with P1 filters.

Where the asbestos removal work area connects either to the outside environment or to the rest of the building, it should be enclosed so that an airtight seal is maintained for the duration of the asbestos removal work (for example, windows, ducts, wall cavities and lift entrances).

All movable items should be removed from the removal area. If this is not possible, move the items from the immediate asbestos removal work area and cover with two layers of plastic sheeting with a minimum overlap of 300 mm between the layers. Both layers should be double taped.

All non-movable items such as fixtures and fittings should be covered with plastic sheeting and the joints sealed.

Airlocks should be placed at the entry points to the change area and constructed using double sets of overlapping plastic with suitable provisions for ensuring a seal.

All floors should be protected with at least one layer of woven plastic to prevent penetration during the removal work. The joints should be lapped 300 mm and sealed with double-sided tape and duct tape.

If the asbestos removal area is next to areas occupied by unprotected persons, priority should be given to:

Consideration should be given to the use of hoarding to form a barrier between the asbestos removal work area and the adjoining occupied areas. A plastic-lined barrier should be erected within this hoarding and a buffer area should be reserved between the hoarding and occupied areas.

Platforms and fixed scaffolding should be erected during the early stages of the work. These structures should ideally be erected on the outside of the enclosed area. Any platforms or fixed scaffolding within the enclosed area must be decontaminated and visually inspected at the end of the removal work.

All tools and equipment used for removal work, including asbestos vacuum cleaners, must remain within the asbestos removal work area until the completion of the job.

All the plastic and tape used for the enclosure must be disposed of as asbestos waste. Any temporary structures must be disposed of as asbestos waste if they cannot be decontaminated. An inspection by a competent person will confirm if the structures are free of any visible asbestos.

Work methods should be adapted for the work environment within the enclosure. For example, rest breaks need to be based on a risk assessment taking into account factors such as the weather and heating/cooling requirements.

Prior to the removal work commencing, the licensed asbestos removalist should ensure the enclosure is tested by a licensed assessor.

A licensed assessor should visually inspect, test and smoke the enclosure prior to commencement of the asbestos removal work.

Negative pressure exhaust units should not be used while the smoke test is being conducted.

The effectiveness of the enclosure should be regularly monitored while asbestos removal work is underway (for example, a visual examination, air-monitoring results and negative pressure readings).

If leaks or deficiencies are found during the initial testing of the enclosure, these must be rectified (an expandable foam sealant, tape or equivalent may be used) and another smoke test performed until no leaks or deficiencies are identified.

Following a visual examination of the enclosure and surrounding area, if a leak of asbestos (more than 0.02 fibres/ml) is detected:

A supply of expandable foam sealant, polyester insulation or equivalent should be kept on site for sealing leaks.

To prevent the escape of airborne asbestos from an enclosed asbestos work area, an exhaust extraction fan should be installed so as to create a ‘negative’ air pressure of approximately 12 Pa (water gauge) within the enclosed asbestos work area.

An exhaust extraction fan should be installed in the enclosure to create a ‘negative’ air pressure of approximately 12 Pa (water gauge) within the enclosed asbestos removal work area. This may require the use of more than one negative pressure exhaust unit.

Units should incorporate warning devices for filter integrity/overload and power failure, and should have a manometer or magnohelic gauge and an audible and visual alarm system.

The negative pressure exhaust unit should be positioned opposite the decontamination unit to enable laminar (smooth) air flow.

The HEPA filter must comply with AS 4260:1997 High efficiency particulate air (HEPA) filters – Classification, construction and performance or its equivalent.

The negative air units should operate continuously (24 hours a day) until all asbestos removal work and decontamination within the enclosure has been completed, a clearance certificate issued and the enclosure dismantled. If the units stop during removal work, the licensed asbestos removalist must ensure all removal work ceases immediately until the problem is rectified and the required number of units are in operation. To minimise the risk of airborne asbestos fibres escaping the enclosure, the delay should be as short as possible to avoid interruption. Consideration should be given to backup negative pressure exhaust units and the use of a generator.

Maintenance work on these units should only be performed after they have been thoroughly decontaminated, or the work may be carried out under controlled conditions, such as in an asbestos removal enclosure while wearing appropriate PPE.

Sprayed asbestos insulations need to be wet thoroughly using a fine water spray. Aim to achieve maximum saturation with minimum run-off to minimise any subsequent clean-up and slip hazards.

Wetting, scraping and vacuuming methods need to be used wherever reasonably practicable. Where the ACM is covered with cloth, metal cladding or wire reinforcing, it should be wet thoroughly during the removal process.

Once a competent person has determined the removal area is clean, the licensed removalist should, wherever reasonably practicable, spray clean surfaces within the removal area with tinted PVA or a similar acrylic emulsion using airless spraying equipment. This includes any layer of plastic forming the inner surface of the enclosure to ensure any loose asbestos fibres on the plastic are firmly adhered to prior to its dismantling.

After the PVA has dried and sufficient time has elapsed for it to dissipate, air (clearance) monitoring should take place, where required. The plastic enclosure must not be dismantled until a satisfactory visual inspection and monitoring has taken place.

The licensed asbestos removalist should only dismantle a structure used to enclose an asbestos removal area once all of the following are done:

The plastic that formed the enclosure must be disposed of as asbestos waste, along with any other contaminated material that assisted in forming the enclosure. In some cases, structures used in building the enclosure (other than the plastic that formed the enclosure) may be wrapped and sealed in plastic and not opened until in a similar controlled environment, such as another asbestos removal enclosure (for example, collapsible rods used to form the enclosure frame).

The area from which the enclosure was dismantled must be thoroughly cleaned and inspected. This should be followed by further air monitoring demonstrating the levels are below 0.01 fibres/ml.

Ropes, warning signs and protective plastic isolating public areas should not be removed until:

The licensed asbestos removalist should ensure an employee is stationed outside the asbestos work area for the duration of the asbestos removal work to:

Records of these checks should be made on a daily basis and kept.


6. METHODS FOR SMALL SCALE REMOVAL WORK

Small scale friable asbestos removal work usually generates enough airborne asbestos fibres to require the use of PPE and generally is carried out only in short periods, for example minor maintenance work. Small scale removal work involves using mini-enclosures, ‘glove bag’ and ‘wrap and cut’ techniques.

Mini-enclosures are suitable for asbestos removal work in areas with restricted access, such as ceiling spaces, and for emergency asbestos removals. Hazards and work procedures that should be considered for large enclosures should also be considered for mini-enclosures.

To build a mini-enclosure, the below process should be followed:

 

Figure 3: Building and using the enclosure.

 

To eliminate or minimise airborne asbestos fibres escaping when dismantling the mini-enclosure, the below process should be followed:

The glove bag removal technique is suitable for the removal of asbestos lagging from individual valves, joints and piping. Glove bags:

The below process should be followed when using the glove bag removal technique:

Figure 4: Example of Glove bag.

 

The ‘wrap and cut’ technique of removal produces the lowest levels of respirable asbestos fibres and is used instead of full containment procedures when the asbestos is a small amount of non-friable asbestos in good condition and not damaged. This method is most appropriate when the entire component is to be removed, such as redundant plant and equipment covered with lagging. If lagging has to be removed to allow a pipe to be cut, the glove bag removal method may be used to expose the metal at the point to be cut and for a sufficient length on either side.

The pipe should be cut at the centre of the exposed section.

The below process should be followed when using the wrap and cut removal technique:

 


7. CONTROLS FOR SPECIFIC ASBESTOS REMOVAL WORK

Appendix D provides some additional examples of asbestos removal work.

Asbestos-contaminated soil comprises non-attached pieces of asbestos cement products and other material containing asbestos uncovered in soil during other work activities. Contamination can be detected during building and road construction and excavation, waste disposal, damage following a severe weather event such as a hail storm, weathering over time, or when asbestos is poorly handled or damaged during removal.

A risk assessment by an independent licensed asbestos assessor or competent person, including contaminated site assessment practitioners, should determine the most appropriate control measures and remediation strategies.

Asbestos-contaminated soil is also subject to requirements of other regulatory agencies such as the EPA, Public Health and local governments. Where guidance on the assessment and remediation of contaminated sites is sought, the Assessment of Contaminated Sites National Environmental Protection Measure (NEPM) should be referred to. The contaminated sites NEPM is published by the Environmental Protection Heritage Council (EPHC).

Removal of asbestos from contaminated soil will require a Class A licensed asbestos removalist for any friable asbestos to be removed, or a Class B licensed asbestos removalist if more than 10 m² of non-friable asbestos is to be removed. A person who does not have a licence can remove 10 m² or less of non-friable asbestos. Where there is uncertainty as to whether the amount of non-friable asbestos is more or less than 10 m², a Class A or Class B licensed asbestos removalist should be engaged.

For all asbestos removal requiring a Class A removal licence, an air monitoring program must be implemented to ensure the control measures do not release airborne asbestos fibre. When all visible asbestos has been removed, and the air monitoring program indicates that the level of respirable asbestos fibres does not exceed 0.01 f/mL (10 per cent of the asbestos exposure standard), the licensed assessor must complete the clearance certificate.

All asbestos and any contaminated soil removed must be disposed of as asbestos waste according to the EPA and the requirements of the local licensed waste disposal facility.

If the soil is suspected of containing asbestos, the person with management or control of the workplace must assume the soil contains asbestos and cease work immediately. A competent person should take samples of the material for analysis to confirm or refute that assumption.

If confirmed, the person with management or control of the workplace must ensure control measures are implemented to minimise the release of airborne asbestos. The control measures include:

Friable asbestos in or on hot metal or machinery presents one of the worst conditions for removal, as airborne asbestos fibres can spread on convection currents in the air and the potential for burns is high.

Removal of work from hot surfaces should be avoided. If possible, the removal should be scheduled and planned around shutdowns, with sufficient time being allowed for the metal or machinery to cool down before removal is attempted. Hot metal removal should be used only in emergency situations and where the use of water sprays may create steam, making the removal task unsafe or more difficult.

In the limited circumstances where the dry removal of asbestos from hot surfaces is the only option (for instance, emergency situations), particular care should be taken in the selection of dust extraction equipment to cope with the convection currents involved, and the selection of appropriate PPE also becomes even more important.

Heat stress should be considered when preparing the asbestos removal control plan, particularly in the selection of PPE and the design of the work program.

Arrangements for the removal of asbestos from hot plant and equipment should be factored into the asbestos management plan for the workplace. This should include cooling requirements and/or the shutdown periods required to achieve adequate cooling.

Asbestos products include gaskets reinforced with asbestos that are used in plant and equipment between flanges on pipes to control the temperature and pressure. Asbestos rope was used for lagging pipes and valves and for sealing hatches. Asbestos is also found in friction products such as brake linings and cylinders. 

It is likely that the asbestos in gaskets and rope and friction products will be friable. This type of plant and equipment is subject to the removal of friable asbestos and may be removed using the ‘glove bag’ or ‘wrap and cut’ method. If the plant contains non-friable asbestos, a Class B licensed asbestos removalist can conduct the removal (which could also be removed by an asbestos removalist that does not have a licence).

In the past, telecommunication pits were constructed using asbestos and at the access points there is potential for exposure to airborne asbestos fibres when accessing these pits.

Work installing or modifying telecommunication lines in these pits may require cutting and removal. Where no other asbestos-related removal work is required and the asbestos is non-friable, a Class B licensed asbestos removalist can remove the asbestos; however, a Class A licensed asbestos removalist may also carry out the removal work. If the amount of non-friable asbestos to be removed is less than 10 m², it may be removed by a person who does not have a licence.


APPENDIX A – ASBESTOS REMOVAL CONTROL PLAN CONTENTS

 

 

Building & structures

Plant & equipment

Friable

Non-Friable

Friable

Non-Friable

Notification

Notification requirements have been met and required documentation will be on site (e.g. removal licence, control plan, training records)

Yes

Yes

Yes

Yes

Identification

Details of asbestos to be removed (e.g. the locations, whether asbestos is friable/non-friable, its type, condition and quantity being removed)

Yes

Yes

Yes

Yes

Preparation

Consult with relevant parties (health and safety representative; workers; person who commissioned the removal work, licensed assessors)

Yes

Yes

Yes

Yes

Assigned responsibilities for the removal

Yes

Yes

Yes

Yes

Program commencement and completion dates

Yes

Yes

Yes

Yes

Emergency plans

Yes

Yes

Yes

Yes

Asbestos removal boundaries, including the type and extent of isolation required and the location of any signs and barriers

Yes

Yes

Yes

Yes

Control of other hazards including electrical and lighting installations

Yes

Yes

Yes

Yes

PPE to be used including RPE

Yes

Yes

Yes

Yes

Removal

Details of air-monitoring program

Control and clearance

Yes

No

Yes

No

Waste storage and disposal program

Yes

Yes

Yes

Yes

Method for removing the asbestos (wet and dry methods)

Yes

Yes

Yes

Yes

Asbestos removal equipment (e.g. spray equipment, asbestos vacuum cleaners, cutting tools)

Yes

Yes

Yes

Yes

Details of required enclosures, including their size, shape, structure etc, smoke testing enclosures and the location of negative pressure exhaust units

Yes

No

Yes

No

Details on temporary buildings required by the asbestos removalist (e.g. decontamination units) including details on water, lighting and power requirements, negative pressure exhaust units and the locations of decontamination units

Yes

May be required depending on the job

Yes

May be required depending on the job

Other risk control measures to prevent the release of airborne asbestos fibres from the area where asbestos removal is undertaken

Yes

Yes

Yes

Yes

Decontamination

Detailed procedures for workplace decontamination, the decontamination of tools and equipment, personal decontamination and the decontamination of non-disposable PPE and RPE

Yes

Yes

Yes

Yes

Waste Disposal

Method of disposing of asbestos wastes, including details on:

  • the disposal of protective clothing

Yes

Yes

Yes

Yes

  • the structures used to enclose the removal area

Yes

No

Yes

Yes

Clearance and air monitoring

Name of the independent licensed asbestos assessor or competent person engaged to conduct air monitoring (if any)

Yes

No

Yes

No

Consultation

Consult with any people who may be affected by the removal work, including neighbours

Yes

Yes

Yes

Yes

APPENDIX B – RESPIRATORY PROTECTIVE EQUIPMENT

When selecting RPE, you should also refer to the AS/NZS 1715:1994 Selection, Use and Maintenance of Respiratory Protective Devices and AS1716:2003 Respiratory Protective Devices.

The figures below provide examples of some respirators that can be used. The protection afforded by each device depends not only on the design and fit of the respirator but also upon the efficiency of the filters (for instance, P1, P2 or P3). These figures are indicative only. In order to show the correct respirator fit, they do not show the use of hoods. Respirators must always be worn under a hood.

Figure 5: Disposable, half-face particulate respirator.

Figure 6: Half-face, particulate filter (cartridge) respirator.

Figure 7: Powered, air-purifying, ventilated respirator.

Figure 8: Full-face, particulate filter (cartridge) respirator.

Figure 9: Full-face, powered air-purifying particulate respirator.

Figure 10: Full-face, positive pressure demand air-line respirator.

The most efficient respirator and filter for the task should be used. Proper fit is critical; a disposable half-face respirator is especially difficult. Consideration should be given to upgrading to a non-disposable half-face respirator.

Table 2 provides guidance for the selection of appropriate respiratory protection for different tasks, assuming the correct work procedures are being followed. This table does not take into account personal features including facial hair or where glasses are worn. Full protection cannot be achieved if either of these factors interferes with the face seal. 

Workers should be consulted on the selection of RPE to ensure individual fit and medical factors have been considered.

Work Procedure

Required respirator

Filter type

Simple enclosure erection for containing undamaged asbestos materials to prevent damage – no direct handling but possible disturbance of asbestos

Disposable, half-face particulate respirators

OR

Half-face, particulate filter (cartridge) respirator

P1 or P2

Inspection of the condition of any installed friable asbestos, which appears in poor condition or has been disturbed

Disposable, half-face particulate respirators

OR

Half-face, particulate filter (cartridge) respirator

P1 or P2

Sampling material for the purpose of identifying asbestos

Disposable, half-face particulate respirators

OR

Half-face, particulate filter (cartridge) respirator

P1 or P2

Removal of non-friable asbestos (e.g. asbestos cement sheets, ceiling tiles and vinyl tiles)

Disposable, half-face particulate respirators

OR

Half-face, particulate filter (cartridge) respirator

P1 or P2

Extensive sample operations on friable asbestos

Full-face, particulate, filter (cartridge) respirator

P3

Maintenance work involving the removal of small quantities of friable asbestos (e.g. replacement of friable asbestos gaskets and insulation)

Full-face, particulate, filter (cartridge) respirator

P3

Certain forms of wet stripping in which wetting is prolonged and effective, and certain small-scale dry stripping operations

Full-face, powered air-purifying particulate respirator

OR

Full-face, positive pressure demand air-line respirator

P3

Certain forms of dry stripping and ineffective wet stripping (light wetting, no time given to saturate)

Full-face, powered air-purifying particulate respirator

OR

Full-face, positive pressure demand air-line respirator

 

No lesser respirator will suffice

P3

Dry stripping in confined areas

Full suit or hood, positive pressure demand continuous flow air-line respirator

 

No lesser respirator will suffice

P3 only as a backup

Table 2: Selecting RPE.

The fit of a negative-pressure respirator to a worker’s face is critical. A fit test, in accordance with AS/NZS 1715:2009 Selection, Use and Maintenance of Respiratory Protective Devices and the manufacturer’s instructions, should be performed to assist in determining the best fit respirator for the individual worker immediately before commencing work and a fit check performed each time the respirator is to be used.

The performance of RPE depends on a good contact between the wearer’s skin and the face seal of the mask so that the mask is a tight-fitting face piece or full mask. A good face seal can only be achieved if the wearer is clean-shaven in the region of the seal and the face piece is the correct size and shape to fit the wearer’s face.

Workers using negative-pressure respirators should also be clean-shaven to ensure a good face seal. Workers with beards, stubble or facial hair should use a continuous-flow positive pressure respirator.

Workers wearing prescription glasses with side arms may not be able to use full-face respirators because of the loss of seal around the spectacle arms. If their glasses cannot be modified so they do not need the support of the ears, these workers should not use full-face respirators and should wear air supply hoods instead. Ensure that these hoods will provide a sufficient level of protection.

Where the half-face respirator has been selected as providing the most appropriate protection and a seal or fit is not achievable from non-disposable respirators, a disposable respirator may be used.  


To conduct a full- or half-face respirator fit check:

 


APPENDIX C – EXAMPLE OF A CLEARANCE CERTIFICATE

 

 

NOTE: Where asbestos removal work requires a Class A licence, a licensed asbestos assessor must carry out the clearance inspection and complete an asbestos removal clearance certificate if satisfied that the area is safe to reoccupy.

 

Client details

Name of client:

 

 

 

 

Client contact details:

 

 

 

 

Removal work details

Date removal work carried out:

 

 

 

 

Site address where removal work is being carried out:

 

 

 

 

Details of the specific asbestos removal work area(s):

 

 

 

 

Name of licensed asbestos removalist:

 

 

 

 

Name and contact details of licensed asbestos removalist supervisor (if different to removalist):

 

 

 

Inspection details

Date of clearance inspection:

 

 

 

 

Time of clearance inspection:

 

 

 

 

 

 

 

Yes

No

Do you have a copy of the asbestos removal control plan ?

 

 

Do you have a copy of the notification form?  

 

 

Is the removal work consistent with the control plan and the notification form? (e.g. use of enclosures, decontamination facilities, waste facilities)

 

 

 

 

 

Yes

No

Inspection of the specific area detailed in Section A found no visible asbestos remaining as a result of the asbestos removal work carried out.

 

 

Is air monitoring required (if no, proceed to Section E)

 

 

Can the area be reoccupied?

 

 

Has additional information been attached? (e.g. photos, drawings, plans)

 

 

 

 

Yes

No

Air monitoring was carried out as part of the clearance inspection. The result was below 0.01 f/ml.

 

 

Has the air monitoring sample been analysed by a NATA-accredited laboratory?

 

 

Is the air monitoring report attached? 

 

 

Can the area be reoccupied? 

 

 

 

 

 

Yes

No

The area within the enclosure and the area immediately surrounding the enclosure was inspected and no visible asbestos was found.

 

 

Air monitoring was carried out as part of the clearance inspection. The result was below 0.01f/ml.

 

 

Is the air monitoring report attached? 

 

 

Can the enclosure be dismantled?

 

 

 

Number of samples collected:____________________

 

Sample 1

Sample 2

Sample 3

Sample 4

Sample 5

RESULTS

 

 

 

 

 

 

 

Yes

No

An inspection of the area in which the enclosure was erected and the area immediately surrounding the area where the enclosure was erected was inspected and no visible asbestos was found.

 

 

Air monitoring was carried out as part of the clearance inspection. The result was below 0.01f/ml.

 

 

Is the air monitoring report attached? 

 

 

Can the area be reoccupied? 

 

 

 

Number of samples collected: ____________________

 

Sample 1

Sample 2

Sample 3

Sample 4

Sample 5

RESULTS

 

 

 

 

 

 

 

 I declare that:

   

 

 

...........................................................

Signature of licensed assessor/competent person

 

 

...........................................................

Assessor licence number (if applicable)

 

 

...........................................................

Name of licensed assessor /competent person

 

  

 


APPENDIX D – EXAMPLES OF ASBESTOS REMOVAL WORK

 

NOTE:  This appendix does not address hazards other than asbestos, including fall from heights or electrical hazards. These hazards also need to be identified and the associated risk controlled.

This appendix provides guidance on how to perform a specific task associated with asbestos removal work.

With all tasks, some general requirements include the following:

Asbestos cement products consist of approximately 15 per cent asbestos fibres by weight. A wide range of products have been commonly foundincluding roofing, shingles, exterior cladding on industrial, public and some domestic premises, corrugated/profile sheets as well as flat sheetsthat have been used for exterior flexible building boards.

If possible, you should remove the asbestos cement products whole. If some sections have been damaged prior to removal, these may be strengthened by applying duct tape.

Identify the method in which the asbestos cement product is held in place, then use a method that would minimise airborne dust generation in removing the product. For example:

Avoid breaking the asbestos cement products. If breakage is absolutely necessary to remove/dislodge the product, dampen the material and minimise breakage.

Remove the asbestos cement product wet/damp by applying a fine water spray, unless this creates an electrical risk.

Once removed from its position, spray the back of the product with a fine water spray. Frequent application of a fine water spray may be required depending on the circumstances (for example, a very hot day) but be careful not to create a slip hazard.

Personal decontamination must be carried out in accordance with the WHS Regulations and this Code.

Asbestos cement can become brittle with age, so any removal work on roofs should address the risk of fall hazards. If lichen is encountered on roof sheeting, caution should be exercised in the use of water and the choice of workers’ footwear because lichen can be slippery, especially when it is wet. 

The removal of asbestos cement roofing must be performed in accordance with the WHS Regulations.

Angle grinders should not be used because of the potential for damage to the asbestos cement and subsequent fibre release. Anchoring screws/bolts should be removed from the roofing sheets using an oxy torch or another suitable device that will not significantly damage the sheet.

If the system of removal involves walking on the roof to remove roof sheeting (this should be the last option when choosing a method to remove roof sheeting), spray the asbestos cement roof sheeting with a PVA solution prior to removal. Ensure the PVA is dry before removing it so as to avoid a slip hazard. Once removed, spray the back (underside) of the asbestos cement with either a fine water spray or the PVA solution.

Where the asbestos cement product requires lowering to the ground, ensure this is done in a manner that will minimise the generation of respirable dust. Do not use chutes, ramps or similar gravity dependent devices. Examples of appropriate lowering methods for roof sheeting include:

You should follow the cleaning, decontamination, waste removal and disposal procedures in this Code once the asbestos sheeting has been removed.

Where the area to be removed is greater than the size of an average domestic house or where considerable dust will be generated, you should use a full decontamination unit.

Ensure that clearance of the area has been completed and a clearance certificate has been issued prior to reoccupation of the area.

Personal decontamination must be carried out in accordance with the WHS Regulations and this Code.

Flooring products such as Polyvinyl chloride (PVC or vinyl) tiles often contain a few per cent (5–7 per cent) of very fine chrysotile. Black and brown thermoplastic tiles containing larger amounts and often visible clumps of chrysotile were also produced. Sheet floor coverings were sometimes backed with a thin layer of chrysotile paper. Some underfelts, such as hessian underlays for carpets and linoleum, were also manufactured containing asbestos. The mastics which were used to bond the floor covering to the surface could also contain asbestos. Some hard-wearing composite floors (for example, magnesium oxychloride) also contain about 2 per cent of mineral fibres, which could be asbestos.

Place a tool (such as a scraper or wide blade) between the tiles and lift the tile away from the floor, being careful to minimise breakage. A hammer or mallet can be used to tap the tool under

Minimise dust by spraying fine water mist under tiles as they are lifted.

Place the tiles into a 200 µm plastic waste bag or suitable alternate waste container dedicated for asbestos waste that is clearly labelled with an appropriate warning sign indicating asbestos waste.

Use the scraper to remove any adhesive that is left adhered to the floor after each tile has been removed and place this waste into the asbestos waste bag or suitable waste container.

The vinyl can be cut into strips prior to its removal to facilitate bagging, or it can be rolled into one roll and wrapped securely with plastic, making sure it is totally sealed.

If a heat source is used to soften the adhesive beneath a vinyl tile, care should be taken not to scorch or burn the tile. Burning or scorching vinyl tiles can result in the release of toxic decomposition products and generate a fire hazard. In some cases, the adhesive may contain asbestos.

Follow the cleaning, decontamination, waste removal and disposal procedures once the tiles have been removed.

Ensure that clearance of the area has been completed prior to reoccupation of the area.

Personal decontamination must be carried out in accordance with the WHS Regulations and this Code.

This material is generally regarded as non-friable and includes bitumen products such as roofing felts and damp-proof courses that have been widely reinforced by the addition of asbestos, usually in the form of chrysotile paper. Bitumen-based wall and floor coverings were also produced.

Some mastics used to stick the bitumen products commonly had asbestos added to them for flexibility. Other sealants also had asbestos added to improve the performance of the product.

When removing bituminous products:

Personal decontamination must be carried out in accordance with the WHS Regulations and this Code.

False ceiling tiles or suspended ceilings sometimes need to be removed so maintenance work can be performed. If asbestos has been used on structural materials above a false ceiling there could be contamination on the upper surface of the tiles.

The minimum respiratory protection suitable for this operation is a P1 or P2 filter with a half-face piece respirator. If considerable amounts of asbestos dust or debris are likely to be involved, full-face air-purifying positive pressure respirators should be worn.

Any surface below the tiles that might be contaminated should be covered with plastic sheeting. 

The first tile should be lifted carefully to minimise the disturbance of any asbestos fibres. The top of each tile should be thoroughly vacuumed and wet wiped, where possible, prior to removing subsequent tiles.

Where non-asbestos ceiling tiles are to be reused, they should be covered with plastic as they are removed from the ceiling to prevent further dust settling on them.

Wrap the asbestos ceiling tiles in a double layer of heavy-duty, 200 μm thick plastic sheeting.

Waste containment, disposal and clearance must be carried out in accordance with the WHS Regulations and this Code.

Personal decontamination must be carried out in accordance with the WHS Regulations and this Code.

This material is generally regarded as friable. If there is any doubt, advice should be sought from a person with knowledge and experience in dealing with asbestos.

Gaskets reinforced with asbestos were once used extensively in plant and equipment exposed to high temperatures and/or pressures. These gaskets were typically used between the flanges of pipes.

Asbestos rope was often used for lagging pipes and valves and for sealing hatches. It is likely that the asbestos in gaskets and rope from plant and equipment will be friable. When removing gaskets and rope seals:

Personal decontamination must be carried out in accordance with the WHS Regulations and this Code.

Asbestos was widely used to insulate pipes, boilers and heat exchangers.

There are several types and forms of insulation, often with multi-layer construction. Pre-formed sections of asbestos insulation were made to fit the diameter of the pipe. These would be strapped on and calico-wrapped and sometimes painted (for example, ‘Decadex’ finish) or sealed with a hard plaster (often asbestos-containing) to protect against knocks and abrasion. Other types of asbestos-containing felts, blankets, tapes, ropes and corrugated papers were also used. For bends and joins, ensure the plant and equipment has been made safe (for example, pipework emptied, electrical supply isolated and equipment shut down).

Set-up/attach the glove bag and perform the removal work as described in this Code. Remove and dispose of waste according to the relevant sections of this Code.

Personal decontamination must be carried out in accordance with the WHS Regulations and this Code.

These are normally homogeneous coatings sprayed or trowelled onto reinforced concrete or steel columns or beams as fireproofing. Sprays were also commonly used on the underside of ceilings for fireproofing and sound and thermal insulation in many high-rise premises. Warehouses and factories commonly had sprayed asbestos applied to walls, ceilings and metal support structures for fireproofing.

Some fire doors contained loose asbestos insulation sandwiched between the wooden or metal facings to give them the appropriate fire rating. Loose asbestos was also packed around electrical cables, sometimes using chicken wire to contain it.

Mattresses containing loose asbestos were widely manufactured for thermal insulation. Acoustic insulation has been provided between floors by the use of loose asbestos in paper bags, and in some areas near removal works it is known that loose asbestos has been used as a readily available form of loft insulation.

Asbestos textiles were manufactured for primary heat (for example, insulation tapes and ropes) or fire protection uses (for example, fire blankets, fire curtains and fire-resistant clothing). Textiles were also used widely as a reinforcing material in friction products/composites.

It will depend on where the fire retardant material is located and the quantity of the material as to how the removal process is conducted, however the asbestos is friable and a Class A licensed asbestos removalist must perform the asbestos removal work. 

An asbestos removal control plan must be developed.

Personal decontamination must be carried out in accordance with the WHS Regulations and this Code.

As asbestos millboard is typically 100 per cent asbestos and very friable. A full enclosure with negative air extraction units must be used for this type of asbestos removal work.

The asbestos millboard should be wetted down as the vinyl is peeled from the floor, preferably with the millboard attached. The vinyl can be cut into strips prior to its removal to facilitate bagging, or it can be rolled into one roll and wrapped securely with plastic, making sure it is totally sealed. If the vinyl sheeting cannot be removed without leaving some of the asbestos millboard on the floor surface, the remaining asbestos millboard should be wetted down and, when thoroughly soaked, scraped off the floor surface.

Sufficient water should be used to dampen the asbestos millboard, but not so much that run-off or pools of contaminated water will occur.

If a heat source is used to soften the adhesive beneath a vinyl tile, care should be taken not to scorch or burn the tile. Burning or scorching vinyl tiles can result in the release of toxic decomposition products and generate a fire hazard.

Alternative removal methods should only be used if they do not result in excessive fibre release from the asbestos millboard and do not result in any additional hazard.

Personal decontamination must be carried out in accordance with the WHS Regulations and this Code.