Christmas Island Utilities and Services (Electricity Supply and Services Fees) Amendment (2021 Measures No. 1) Determination 2021
I, Natasha Griggs, Administrator of the Territory of Christmas Island, make the following determination.
Dated 13 December 2021
Natasha Griggs
Administrator of the Territory of Christmas Island
Contents
1 Name
2 Commencement
3 Authority
4 Schedules
Schedule 1—Amendments
Christmas Island Utilities and Services (Electricity Supply and Services Fees) Determination 2016
This instrument is the Christmas Island Utilities and Services (Electricity Supply and Services Fees) Amendment (2021 Measures No. 1) Determination 2021.
(1) Each provision of this instrument specified in column 1 of the table commences, or is taken to have commenced, in accordance with column 2 of the table. Any other statement in column 2 has effect according to its terms.
Commencement information | ||
Column 1 | Column 2 | Column 3 |
Provisions | Commencement | Date/Details |
1. The whole of this instrument | 1 January 2022. | 1 January 2022 |
Note: This table relates only to the provisions of this instrument as originally made. It will not be amended to deal with any later amendments of this instrument.
(2) Any information in column 3 of the table is not part of this instrument. Information may be inserted in this column, or information in it may be edited, in any published version of this instrument.
This instrument is made under paragraph 7(2)(a) of the Christmas Island Utilities and Services Ordinance 2016.
Each instrument that is specified in a Schedule to this instrument is amended or repealed as set out in the applicable items in the Schedule concerned, and any other item in a Schedule to this instrument has effect according to its terms.
Christmas Island Utilities and Services (Electricity Supply and Services Fees) Determination 2016
1 Subsection 6(2)
Omit “1 November 2020”, substitute “1 January 2022”.
2 Clause 1 of Schedule 1 (table)
Repeal the table (not including the note), substitute:
Fixed fees for the supply of electricity | ||
Item | Column 1 Category of premises | Column 2 Fixed fee (cents per day) |
1 | Residential A2 | 95.5818 |
2 | Community service C2 | 92.2273 |
3 | Charitable residential D2 | 90.9727 |
4 | Business/residential K2 | 168.6636 |
5 | Business and local government L2 | 170.6364 |
6 | Government (other than local government) N2 | 589.0909 |
3 Clause 1 of Schedule 2 (table)
Repeal the table (not including the note), substitute:
Consumption fees for the supply of electricity | ||
Item | Column 1 Category of premises | Column 2 Consumption fee |
1 | Residential A2 | 26.6612 cents per unit consumed |
2 | Community service C2 | For each day, the sum of the following: (a) for the first 20 units consumed—21.5486 cents per unit; (b) for the next 1,630 units consumed—22.9909 cents per unit; (c) for each subsequent unit consumed—21.9300 cents per unit |
3 | Charitable residential D2 | 23.1135 cents per unit consumed |
4 | Business/residential K2 | For each day, the sum of the following: (a) for the first 20 units consumed—27.8524 cents per unit; (b) for the next 1,630 units consumed—26.2472 cents per unit; (c) for each subsequent unit consumed—29.5927 cents per unit |
5 | Business and local government L2 | For each day, the sum of the following: (a) for the first 1,650 units consumed—26.5535 cents per unit; (b) for each subsequent unit consumed—29.9382 cents per unit |
6 | Government (other than local government) N2 | 50.6455 cents per unit consumed |
4 Clause 1 of Schedule 3 (table item 3)