Greenhouse and Energy Minimum Standards (Exemption) Instrument (No. 2) 2024
I, Lachlan Bickley, being the person occupying the position of GEMS Regulator, make the following instrument.
Dated 22 August 2024
Lachlan Bickley
GEMS Regulator
Contents
1 Name
2 Commencement
3 Authority
4 Definitions
5 Exemption
6 Repeal
Schedule 1—Exemption
This instrument is the Greenhouse and Energy Minimum Standards (Exemption) Instrument (No. 2) 2024.
This instrument commences on the day after it is registered on the Federal Register of Legislation.
This instrument is made under subsection 37(1) of the Greenhouse and Energy Minimum Standards Act 2012.
In this instrument:
Determination means the Greenhouse and Energy Minimum Standards (Household Refrigerating Appliances) Determination 2019.
exempt models: see section 5.
The models specified in clause 1 of Schedule 1 (the exempt models) are exempt from the requirements of the Determination as described at clause 2 of Schedule 1 with respect to the supplies of the exempt models specified at clause 3 of Schedule 1.
This instrument is repealed 12 months after coming into effect.
1 Specification of exempt models
| Brand | Model Number |
1 | Asko | RFN31841l |
2 Requirements from which models are exempt
Requirements of the Determination as follows:
GEMS level requirements | The identified models are exempted from the GEMS level requirements, which are set out in part 8 of the Determination. |
GEMS labelling requirements | The identified models are exempted from the GEMS labelling requirements, which are set out in part 9 of the Determination. |
GEMS other requirements | The identified models are exempted from the GEMS other requirements, which are set out in part 10 of the Determination. |
3 Supplies to which the exemption applies
This exemption applies in relation to any supplies of refrigerators with the specifications set out in clause 1 of this Schedule.